首页> 外文会议>International symposium on reviewing the safety of existing nuclear power plants >SAFETY REVIEW FOLLOWING INSIGHTS INTO A MAJOR EVENT AT BAERSEBAECK 2 A Swedish example-course of action
【24h】

SAFETY REVIEW FOLLOWING INSIGHTS INTO A MAJOR EVENT AT BAERSEBAECK 2 A Swedish example-course of action

机译:安全审查后深入了解Baersebaeck 2瑞典举例的一项瑞典举例

获取原文

摘要

When Baersebaeck 2 was restarted after the annual outage on 28 July 1992, a safety relief valve opened inadvertently at less than 2% power and 3.0 MPa reactor pressure. This was caused by a leaking pilot valve which had been assembled incorrectly. The leaking pilot valve caused depressurization of the main valve, which then opened. When the main valve opened, the reactor pressure acted on the rupture disc in this valve. When the reactor pressure reached 3 MPa, the rupture disc broke and a jet of steam was released into the containment. The containment was isolated and the containment vessel spray system (CVSS) and the emergency core cooling system were automatically started. The steam jet caused mineral insulation material to be dislodged from the pipes situated close to the safety relief valve. Insulation material was flying about in the containment. The amount of dislodged insulation material was about 200 kg; approximately 100 kg of this material was flushed down into the condensation pool by steam flow and by water flow from the CVSS. This incident did not jeopardize the safety of the plant, but further investigation and remediation were required because of the potential of the incident. In order to restore the safety of nuclear plants with a similar design, five of the Swedish plants were forced by the Swedish Nuclear Power Inspectorate (SKI) to shut down. The conditions for resuming plant operation were that temporary modifications should be made and that the safety function analysis in probabilistic terms should be shown to be equivalent to the original safety analysis. Four of the plants were able to restart approximately six months after the event. At Oskarshamn 1, other safety deficiencies were found during the outage; these required a longer outage period in order to restore the level of safety commonly assumed to be necessary at that time. In the modification and control project for Oskarshamn 1, called FENIX, the first step, FENIX Restart, aimed at performing the modifications required to obtain permission for continuation of plant operation. In order to meet long term demands for safety, the FENIX project also initiated a modernization programme, plans for which had been made in parallel with the implementation of the FENIX Restart programme. This modernization will be performed in several steps during the yearly outages in the period 1996-1999. The deficiencies found at Oskarshamn 1 forced the utility to perform a much larger inspection, control and modification programme than had initially been anticipated. SKI requested that, before restart of the plant, a complementary safety report should be submitted to it, with an overall evaluation of plant safety. Plant modifications made at Barseback 2 within the FENIX project are described in the paper. When the FENIX project reached its major milestone-restart of Oskarshamn 1, it had demonstrated that the plant was in a better state than had been evaluated in 1992, before the event at Barseback. However,
机译:1992年7月28日在年度停机后重新启动了BaerseBaeck 2时,安全释放阀在不到2%的功率和3.0MPa反应器压力下无意中打开。这是由泄漏的先导阀引起的,该阀门被错误地组装。泄漏的导阀导致主阀的减压,然后打开。当主阀打开时,电抗器压力在该阀中的破裂盘上作用。当反应器压力达到3MPa时,破裂盘破裂和蒸汽射流被释放到容纳中。将储存储存,并自动启动容纳血管喷雾系统(CVS)和应急核心冷却系统。蒸汽喷射使矿物绝缘材料从位于安全释放阀靠近的管道上脱落。绝缘材料在容纳中飞行。脱落的绝缘材料的量约为200kg;通过蒸汽流动并通过来自CVSS的水流将大约100kg这种材料冲入冷凝池中。这一事件没有危及工厂的安全性,但由于事件的潜力,需要进一步调查和修复。为了恢复具有类似设计的核电站的安全性,瑞典核电监察署(SKI)迫使瑞典植物中的五个植物关闭。恢复工厂操作的条件是应制定临时修改,并且应显示概率术语的安全功能分析等同于原始安全分析。植物中的四个植物能够在事件发生后大约六个月重新开始。在Oskarshamn 1,中断期间发现了其他安全缺陷;这些需要更长的停电时间,以便在当时恢复常见的安全水平。在Oskarshamn 1的修改和控制项目中,称为Fenix,第一步,Fenix重启,旨在执行获得延续植物操作允许的修改。为了满足安全的长期需求,Fenix项目还发起了现代化计划,计划与Fenix重启程序的实施并行进行。这次现代化将在1996 - 1999年期间在年度停电期间进行了几步。在Oskarshamn 1中发现的缺陷强制使用该实用程序,而不是最初预期的更大的检查,控制和修改程序。 SKI要求,在重新启动工厂之前,应提交互补的安全报告,并进行整体评估工厂安全。在Fenix项目中的BARSEBACK 2在FENIX项目中进行了植物修改。当Fenix项目达到其主要的Milestone重启Oskarshamn 1时,它表明,在BarseBack的活动之前,该工厂始于1992年的评估更好。然而,

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号