MODELING THE PRODUCTIVITY OF PRE-CAST CONCRETE INSTALLATION

机译:模拟预制混凝土安装的生产率

获取原文
获取原文并翻译 | 示例

摘要

The production process of pre-cast concrete installation is analyzed to investigate possible ways for onsite productivity improvement. System productivity is measured in order to synchronize factory daily production. Although manufactured construction enjoys higher quality and productivity, it is observed that it suffers delays compared to site built construction. Delay causes and severity are analyzed further for improvement.The production process is investigated using the method productivity delay model (MPDM). Productivity measures obtained via the MPDM are compared to the results of a statistical analysis performed on the cycle time data. Forty cycle data are used in the analysis. Another data set of detailed 90 production cycles are used for statistical analysis for the installation of three pre-cast component products. The MPDM is used to measure the comparative impact and severity of five delay causes namely: labor, environmental, management, equipment, and material on overall system productivity. It is found that material, followed by equipment then labor availability are major contributors to system delay. Improvement can be achieved through a proper scheduling of project equipment and resources.
机译:分析了预制混凝土安装的生产过程,以研究提高现场生产率的可能方法。测量系统生产率是为了同步工厂的日常生产。尽管制造的建筑享有更高的质量和生产率,但据观察,与现场建造的建筑相比,它遭受了延误。进一步分析了延迟原因和严重性以进行改进。使用生产率延迟模型(MPDM)研究生产过程。将通过MPDM获得的生产率指标与对周期时间数据进行统计分析的结果进行比较。分析中使用了40个周期的数据。详细的90个生产周期的另一个数据集用于统计分析三个预制组件产品的安装。 MPDM用于衡量五个延迟原因的相对影响和严重性,这些原因是:劳动力,环境,管理,设备和材料对整体系统生产率的影响。已经发现,材料,其次是设备,然后是劳动力可用性是造成系统延迟的主要因素。可以通过适当安排项目设备和资源来实现改进。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号