METHOD AND SYSTEM FOR ASSESSING THE PROGRESS OF A PROJECT IN TERMS OF ITS SCHEDULE
METHOD AND SYSTEM FOR ASSESSING THE PROGRESS OF A PROJECT IN TERMS OF ITS SCHEDULE
展开▼
机译:评估项目进度表中项目进度的方法和系统
展开▼
页面导航
摘要
著录项
相似文献
摘要
The invention describes a computer-implemented method and system for assessing the progress of a project in terms of its schedule. The method includes receiving project data and based on the project data, calculating a first period (PE) after which a current earned value (EV) was expected to be realized. The method also includes calculating a second period (PR) in which the current EV has been realized. Further, the method includes calculating a fraction component (EF) of a period when the current EV was expected to be realized and finally, calculating an earned schedule performance index (ESPI) based on PE, PR and EF, wherein the ESPI indicates whether the project is on schedule.