首页> 外文期刊>The HKIE Transactions >Trenchless construction of Phase IIIA district cooling system (DCS) by TBM pipejacking and hand-dug tunnelling on Kai Tak Development: part I - design and construction considerations
【24h】

Trenchless construction of Phase IIIA district cooling system (DCS) by TBM pipejacking and hand-dug tunnelling on Kai Tak Development: part I - design and construction considerations

机译:TBM管道和手动隧穿阶段IIIA区冷却系统(DCS)的轨道建设:凯德开发:第一部分 - 设计和施工考虑

获取原文
获取原文并翻译 | 示例
           

摘要

In this paper, the design and construction of 1.75 km of 1200 mm, 1500 mm and 2800 mm diameter concrete sleeve pipelines, using slurry operated tunnel boring machines (TBM), for installation of district cooling system (DCS) pipelines, in highly variable ground conditions in the Kowloon Bay area are discussed. This was the first time that TBM pipejacking has been used in Hong Kong to construct pipelines below the seabed. The construction techniques for working pits to suit site constraints are also discussed. Hand-dug tunnels, constructed with hand-mining shield and horizontal pipe-piles, for DCS pipeline installation, due to the constraints by utilities and interfacing contracts, are highlighted.
机译:在本文中,设计和施工1.75米,1200毫米,1500毫米和2800毫米直径的混凝土套管管道,采用浆料操作隧道镗床(TBM),用于安装区域冷却系统(DCS)管道,在高度可变地面 讨论了九龙湾地区的条件。 这是第一次在香港使用TBM管道,以构建海底下方的管道。 还讨论了适合站点限制的工作坑的施工技术。 用手工采矿屏蔽和水平管道构造的手工挖隧道,突出了由公用事业和接口合同的限制而构建的DCS管道安装。

著录项

相似文献

  • 外文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号