Replacement of shutdown cooling system and repair of nozzle welds of reactor pressure vessel in Forsmark 1 + 2 nuclear power plant

机译:Forsmark 1 + 2核电站的停机冷却系统更换和​​反应堆压力容器喷嘴焊缝的维修

获取原文
获取原文并翻译 | 示例
           

摘要

The Forsmark nuclear power plant consists of three units with boiling water reactors. Unit 1 and Unit 2 were put into operation in 1981 and 1982. Both of these units are of identical design, each having a capacity of 970 MW. Unit 3 was completed in 1985 and has a capacity of 1160MW. In November 1998 Siemens was awarded a Contract to replace the pipework of the two-sectioned Shutdown Cooling System 321 from the nozzles at the reactor pressure vessel to ten meters outside the containment. Moreover, the inner and outer isolation valves including the penetrations were to be replaced. Finally, the repair of the RPV connecting welds of the System 415 (feedwater) and System 323 (emergency cooling) was to be performed.
机译:福斯马克核电站由三个带沸水反应堆的机组组成。 1号机组和2号机组分别于1981年和1982年投入运行。这两个机组的设计均相同,容量分别为970 MW。 3号机组于1985年建成,容量为1160MW。 1998年11月,西门子获得了一项合同,将两段式关机冷却系统321的管道从反应堆压力容器的喷嘴更换到安全壳外十米处。此外,包括通孔在内的内部和外部隔离阀也将被更换。最后,要对系统415(给水)和系统323(紧急冷却)的RPV连接焊缝进行维修。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号