Gotthard drives push ahead

机译:Gotthard驱动器向前推进

获取原文
获取原文并翻译 | 示例
           

摘要

Almost three quarters of the tunnel excavation and nearly two-thirds of the invert lining on the 57km long twin bore Gotthard Base Tunnel had been completed by the beginning of last month, which also saw the trackwork and equipment contract having been finally signed.By the beginning of May, a total of almost 110km of tunnels, galleries and passages had been excavated on the project out of 153km. The total length of drives during April was 1,090m. So far, of the total 113km of concreting works required, 61 % of the invert has been lined and 38% of the vault.
机译:上个月初,这条57公里长的双孔圣哥达基础隧道的隧道开挖工作近四分之三和倒衬的近三分之二已经完工,而且轨道工程和设备合同也已最终签署。 5月初,该项目共开挖了153公里之外的近110公里的隧道,画廊和通道。 4月份驱动器的总长度为1,090m。到目前为止,在总共113公里的混凝土工程中,有61%的内陆衬砌和38%的拱顶衬砌。