Construction Time Analysis For Different Steps In Drill-And-Blast Method Of Hydro Power Tunnel Excavation

机译:水电隧洞开挖爆破施工各步骤施工时间分析

获取原文
           

摘要

One of the most important factors influencing the decision whether and how a tunnel is to be built are the estimated time and costs of construction. This study is based on construction time analysis for different steps in drill-and-blast method of hydro power tunnel excavation in working phase of 6.256,00 meters of tunnels which have different diameters varying from 4,20 to 7,60. There are made 737 field measurements and it is seen that many of the machinery and workmanship productions rates per unit time are significantly lower, varying from 35% to 50%, of that defined in their technical specifications, measurements indicate that highest performance is reached in 7,60m diameter tunnel excavation. It is believed that these data will be helpful for planning and management process of tunnel construction projects, especially those planned to be built in Albania where labor market carries similar features.
机译:影响决定是否以及如何建造隧道的决定的最重要因素之一是估计的时间和建造成本。本研究基于对水力隧洞开挖钻爆法施工阶段6.256,00米长的隧道(不同直径在4,20至7,60之间)的不同步骤的施工时间分析。进行了737现场测量,发现单位时间内的许多机械和工艺生产率都大大降低,从其技术规格中定义的35%到50%不等,测量表明,达到了最高的性能。直径7.60m的隧道开挖。相信这些数据将有助于隧道建设项目的规划和管理过程,尤其是那些计划在劳动力市场具有类似特征的阿尔巴尼亚建造的项目。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号