首页> 外文期刊>Independent Journal of Management & Production >Optimization of times and costs of project of horizontal laminator production using PERT/CPM technical
【24h】

Optimization of times and costs of project of horizontal laminator production using PERT/CPM technical

机译:使用PERT / CPM技术优化水平复合机生产项目的时间和成本

获取原文
           

摘要

The PERT/CPM is a technique widely used in both the scheduling and in the project feasibility in terms of cost control and time. In order to optimize time and costs involved in production, the work presented here aims to apply the PERT/CPM technique in the production project of the Horizontal Laminator, a machine used to cut polyurethane foam blocks in the mattresses industries. For the application of PERT/CPM technique in the project of Horizontal Laminator production were identified the activities that compose the project, the dependence between them, the normal and accelerated durations and the normal and accelerated costs. In this study, deterministic estimates for the duration of the activities were considered. The results show that the project can be completed in 520 hours at a total cost of R$7,042.50, when all activities are performed in their normal durations. When all the activities that compose the critical path are accelerated, the project can be completed in 333.3 hours at a total cost of R$9,263.01. If the activities slacks have been exploited, it can obtain a final total cost of R$6,157.8, without changing the new duration of the project. It is noteworthy that the final total cost of the project if the slacks are used, will be lower than the initial cost. Regarding the initial cost of the project, after the application of the PERT/CPM technique, it presents a decrease of 12.56% of the total project cost.
机译:PERT / CPM是一项在成本控制和时间方面广泛用于进度安排和项目可行性的技术。为了优化生产中的时间和成本,此处介绍的工作旨在将PERT / CPM技术应用于卧式层压机的生产项目中,该机是用于切割床垫行业中的聚氨酯泡沫块的机器。为了将PERT / CPM技术应用到卧式覆膜机生产项目中,确定了构成项目的活动,活动之间的依赖关系,正常和加速工期以及正常和加速成本。在这项研究中,考虑了活动持续时间的确定性估计。结果表明,如果所有活动均在正常时间内进行,则该项目可以在520小时内完成,总费用为7,042.50雷亚尔。当加快构成关键路径的所有活动的速度时,该项目可以在333.3小时内完成,总费用为9,263.01雷亚尔。如果利用了活动的余地,则可以在不改变项目新期限的情况下获得最终总成本6,157.8雷亚尔。值得注意的是,如果使用松弛,则项目的最终总成本将低于初始成本。关于项目的初始成本,在应用PERT / CPM技术后,占项目总成本的12.56%。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号