Significant Operation Efficiency Improvement of Cased Hole Gravel Pack Completion by Implementing Factory Completion Strategy

机译:通过实施工厂完成策略完成套管砾石包装的显着运行效率改进

获取原文

摘要

Zawtika gas field lies approximately 300 km south of Yangon in the Gulf of Mottama,offshore Myanmar focused on laminated Plio-Pleistocene reservoirs.The formations comprises of mixed deltaic and young shallow marine clastic sediments considered amongst the shallowest unconsolidated,poorly sorted with a high percentage of fine sands on the planet.Phase 1A sand control development wells Basis of Design(BoD)underwent considerable extensive laboratory core testing,equipment & stimulation design verification studies prior to successfully completing Seventeen(17)Wells on three(3)Wellhead Platforms.Four(4)additional Platforms with thirty six(36)wells planned to be completed during Phase 1B and further plans to increase Platforms numbers in subsequent Phases.The optimum Cased Hole Gravel Pack(CHGP)completion design shall allow the well to maintain solid-free gas production with selectivity,longevity and integrity throughout the life cycle.This type of completion design was implemented for the first time in PTTEP during Zawtika development,Phase 1A.Due to its complexity and its criticality to the success of the well,the operational approach implemented in Phase 1A was focused more on conservative approach rather than the performance optimization in order to ensure the success and to prove the design concept.The operation went successful and achieved all objectives; where the average times for completing a single and a dual-zone CHGP well were thirteen(13)and eighteen(18)days respectively.Since the CHGP completion design of the Phase 1A proved to be a great success where most of the wells can produce as per or better than the design expectation solids free,the significant operation efficiency improvement drive is one of the main targets of the Zawtika Phase 1B.PTTEPI reviewed Phase 1A post-completion operations and tendered the work with similar design specifications based on the fact that earlier wells completed with Sand Control continued to produce at expected gas rates solids free.In order to improve operational efficiency,many areas were investigated i.e.operational steps,procedures,lesson learns,equipment designs,rig up diagrams,site layouts and integrated knowledge from the Gulf of Thailand(GOT)drilling practices such as batch operation and offline activities were analyzed for implementation in Phase 1B.Concept of Batch Completion strategy is continued and improved from previous Phase 1A that used a Hydraulic Workover Unit(HWU)deployment method onto Phase 1B utilizing a new generation Tender Assisted Drilling(TAD)Rig with Offline Activity Cantilever(OAC)with further emphasis on batch completion approach.To implement a step change in batch completion strategy,the new concept called "Factory-Batch CHGP Completion Strategy" involving comprehensive detailed job planning,semi-permanent pumping package rig up concept,fit for purpose and robust-design of completion equipment,living Standard Operating Procedure(SOP)documents,full implementation of Simultaneous Operation(SIMOP),effective lessons learnt captured and shared,including cross trainings of all parties on the rig site are the main key factors that contribute to the improved operation safety & efficiency.By incorporating and implementing all these factors,PTTEPI is able to reduce the CHGP completion time and cost of Zawtika Development Phase 1B more than 67% comparing to Phase 1A performances in 2014 – 2015.This paper summarizes the fundamental conceptual approach and detailed features of PTTEPI's "Factory-Batch CHGP Completion Strategy" executed in Zawtika Sand Control Development,Phase 1B.
机译:Zawtika Gas Field在亚龙湾南部南部约300公里处于乌马达湾,专注于层压的Plioistocene储层。组合包括混合的Deltaic和年轻的浅海洋碎屑沉积物,认为是较浅的未掩盖,较低的百分比在地球上的细砂。在三(3)个井口平台上成功完成17(17)个井之前,设计设计(BOD)的设计(BOD)的设计(BOD)进行了相当大广泛的实验室核心测试,设备和刺激设计验证研究.Four (4)计划在第1B阶段完成三十六(36)孔的附加平台,并进一步计划在随后的阶段增加平台数量。最佳壳体砾石包装(CHGP)完成设计应使井保持不稳定在整个生命周期中选择性,长寿和完整性的气体生产。这类完工设计是为的在Zawtika开发期间第一次在PTTEP期间,阶段1A.Due对其复杂性及其对井成功的关键性,在第1A阶段实施的操作方法更加集中在保守方法中,而不是绩效优化,以确保成功和成功证明设计理念。操作取得了成功并取得了所有目标;在完成单一和双区Chgp的平均时间分别为13(13)和18天(18)天。SINCE阶段1A的CHGP完成设计被证明是大多数井可以产生的巨大成功按或优于设计预期固体免费的,显著提高作业效率驱动器的Zawtika阶段1B.PTTEPI的主要目标之一审查1A阶段后完成作业和招标基于这样的事实,类似的设计规范工作随着砂控制完成的早期井继续生产预期的天然气率固体。为了提高运营效率,调查了许多地区的重组步骤,程序,课程学习,设备设计,装备图,网站布局和综合知识分析泰国湾(GOT)钻探实践,如批量操作和离线活动,以实施第1B阶段。批次完成策略概念从先前的第1A阶段继续和改进,使用液压器械单元(HWU)部署方法在阶段1b上利用新一代柔软的辅助钻井(TAD)钻机,其中具有离线活动悬臂(OAC),进一步强调批量完成方法。实现在批处理完成战略的阶跃变化,新的概念叫做“工厂批量CHGP完成工作战略”,涉及全面详细的工作计划,半永久抽包搭起的概念,适合目的和完井设备强大的设计,生活标准操作程序(SOP)文件,全面实施同时运作(SIMOP),捕获和共享的有效经验教训,包括钻机现场各方的交叉培训是有助于改善运营安全性和效率的主要关键因素。在纳入和实施所有这些因素,PTTEPI都能够降低ZAWTIKA开发阶段1B的CHGP完成时间和成本超过67%比较2014年至2015年第1A期表演。本文总结了在Zawtika Sand控制开发,1B阶段执行的PTTEPI“工厂批量CHGP完成策略”的基本概念方法和详细特征。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号