The First Successful Experience of Directional Casing Drilling Technology in Timano-Pechora Region, Russia

机译:俄罗斯蒂纳诺 - Pechora地区定向套管钻井技术的第一个成功经验

获取原文

摘要

Well drilling is a very technologically complicated process which consists of different stages and operations. Using different technologies to reduce well construction time is important to optimize well drilling costs. Geological complications can increase the time for pulling out the bottom hole assembly (BHA), condition the well, and running casing. Several studies have shown that nondrilling non-productive time (NPT) is significantly higher than actual drilling time. Casing while drilling (CWD) technology is a unique solution which helps to reduce well construction time in challenging formations while drilling and casing the well simultaneously. Conventional drilling process involves drilling and casing sections in separate operations. CWD involves integrating the casing run process with the drilling process. In casing while drilling, the bottom hole assembly is attached to the casing using a drill lock assembly (DLA). It is challenging to drill and case directional well because the BHA consists of specialized directional tools such as a bend motor, rotary steerable tools, measuring while drilling tools, etc. After reaching the required depth by using specialized tools, the directional BHA is retrieved and casing is cemented. Pilot test runs for directional casing drilling with retrievable bottom hole assembly technology were successfully conducted in Timano-Pechora region. Three directional wells were drilled with CWD technology on 244,5 mm (9 5/8") casing. There was no NPT during the operations. Casing while drilling technology alongside a steerable and retrievable BHA enabled the operator to drill a directional section in soft and unstable rock, hold trajectory according to plan and meet necessary dogleg severity, exclude the possibility of stuck pipe, and reduce well construction time by decreasing the number of wiper trips in open hole. The pilot experience helped to determine the advantages of casing drilling with a retrievable BHA in the specific conditions of the Timano-Pechora region. Tips for improvement and optimizations were highlighted for future reference of that technology in the region.
机译:钻井是一种非常简洁的过程,包括不同的阶段和操作。利用不同的技术来减少良好的施工时间,重要的是优化钻井成本。地质并发症可以增加拉出底部孔组件(BHA)的时间,调节井和运行壳体。几项研究表明,非妥善的非生产时间(NPT)明显高于实际钻井时间。钻井(CWD)技术的同时是一种独特的解决方案,有助于减少富有挑战性地层的良好施工时间,同时钻孔和套接井。传统的钻井过程涉及单独操作中的钻孔和套管部分。 CWD涉及将壳体运行过程与钻井过程集成。在钻孔时在壳体中,使用钻锁组件(DLA)附接到壳体上的底部孔组件。钻孔和案例方向井是挑战,因为BHA由专门的方向工具组成,例如弯曲电机,旋转可转向工具,测量在钻孔工具等时测量等。通过使用专业工具达到所需深度后,检索定向BHA和套管粘合。在Timano-Pechora地区成功进行了具有可检索的底部孔组件技术的定向套管钻孔的试验试验。在244,5毫米(9 5/8“)套管上使用CWD技术进行三个方向孔。操作期间没有NPT。套管钻孔技术与可转向和可检索的BHA一起,使操作员能够在柔软的方向上钻取定向部分和不稳定的岩石,按照计划保持轨迹并满足必要的狗屎严重程度,排除了卡住管道的可能性,并通过减少开孔中的刮水器的数量来减少井的施工时间。试验体验有助于确定套管钻孔的优势在Timano-Pechora地区的特定条件下可检索的BHA。突出了改进和优化的提示,以便在该地区该技术的未来参考。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号