首页> 外国专利> Segmental precast concrete ventilating slabs of structure and construction way in tunnel for rapid installation

Segmental precast concrete ventilating slabs of structure and construction way in tunnel for rapid installation

机译:隧道隧道结构与施工方式的节段预制混凝土板快速安装

摘要

The present invention is provided with a wind guide slab 150 that crosses the upper side of the spring line 91 in the tunnel 90 to supply and exhaust air inside the tunnel structure, and when a cross flow method is applied, the wind guide slab 110 ) Install a bulkhead 150 that vertically partitions between the crown portion of the tunnel lining 100 and the windpipe slab 110 and the pressure jaw 101 from the upper surface side, or a tunnel without a bulkhead 150 as in the case of a semi-cross flow type In installing the tunnel wind slab 200 of any one of the facilities for internal ventilation, The bracket 110 protruding to the inside of the tunnel lining 100, and the wind slab 110 divided into both sections inclined upward from the bracket, the pressure jaw 101, which is a protrusion, is formed on the central side, and the inside The edge 103 side of the wind guide slab 110, which has created several cavities 102 in the transverse direction, is placed in the tunnel lining 100 bracket 104, respectively, and protrudes from the edge of the sectioned slabs 110' and 110". The stopper 105, which is the drawn out reinforcing bar 119, is mounted in close contact with the tunnel lining 100, and the pressure jaw 101, which is a protrusion on the central side, forms a mutual butt between the cut-out slabs 110' and 110" on both sides. And the wind slab 110, When the windmill slab 110 is mounted, several sets of cut slabs 110', 110" on one side and the other side in the production and yard outside the tunnel pit are placed on the first bogie 200' in the shape of a hat. Put it on the tunnel lining 100 and move the stroke of the control hydraulic jack 209 disposed on the main beam 201 so that it can pass over the bracket 104 in a lifted state, and several sets of wind slabs 110 ) In order to ensure that the end 103 side is mounted on the bracket 104 of the tunnel lining 100 at the same time, if the stroke of the hydraulic jack 202 at the upper end of the first bogie 200 ′ transverse beam 203 is gradually lowered, the single-piece slab (110 ', 110 ") The pressure jaws 101 on both sides are automatically brought into contact with each other so that the compression force 101 due to their own weight is introduced into the slabs 110 ', 110 " on both sides along the slope of the hat. method and Here, after first lowering the stroke of the control hydraulic jack 209 disposed on the main beam of the first bogie 200', the first bogie 200' is completely separated from the wind slab 110, and then the first bogie 200' is the upper end. Since the chain block 206 disposed on the 2, lowering the tunnel lining 100 to below the bracket 104 face to form the first entry bogie 200', cross the other entering first bogie 200', and the wind road outside the tunnel and to move the slab 110 to the production site and the yard; As another method, the second bogie 200" lowers the stroke disposed between the main beams 201 so that the transverse beam 203 is horizontal, and then the C-shaped steel 207 installed on either side of the transverse beam 203 is selected. After entering the other transverse beam 203 and entering the C-beam 207 installed on the other transverse beam 203 into the transverse beam 203 on either side to form a structure that does not shake, the tunnel 80, out-of-pit wind slab 110 manufacturing site and Two methods of mounting so that it can be moved to the yard; When mounting the wind slab 110 in a state where the exposed reinforcing bar bracket 113 is installed, the lifting and lowering of the control hydraulic jack 209 of any one of the first bogie 200' and the second bogie 200" is controlled. 3 methods of mounting configured to pass through the bracket reinforcing bar 124 of the exposed reinforcing bar bracket 113 using In the above, the bracket 104, which is an obstacle to mounting the wind slab 110, is separated from the existing shape and composed of an exposed reinforcing bar bracket 113, which is a horizontal and inclined hole 114 in the tunnel lining 110. In the state where the screw-type small steel pipe 135 is embedded and fixed, and the bracket reinforcing bar 124 is installed and bound, when mounted on the second bogie 200", both side sectioned slabs (110', 110") The bracket reinforcing bar 124 of the exposed reinforcing bar bracket 113 is passed through the line port 132 installed on the 103) side, and the bent steel plate 116 with the rubber packing 117 attached to the edge is applied to the exposed reinforcing bar bracket 113. After placing the rubber pad 141 in a state where it is inserted into the upper reinforcing bar to form an uneven portion, the cut slabs 110' and 110" are mounted, but the edge 103 lower groove 115 is a bent steel plate 116 iron To fit into the (凸) part, to be combined with a bolt and nut (BN), to install a reinforcing bar 125, and to install a non-shrinkable mortar 118 to the bent part; The soft bracket 104 on the tunnel lining 100 is installed intermittently, not continuously, forming a certain length, and the intermittent bracket 104 is installed with the exposed reinforcing bar bracket 113 as described above. The bracket reinforcing bar 124 of the exposed reinforcing bar bracket 113 is passed through the line port 132 installed on the edge 103 side of both sides of the In a state in which the cut slabs 110' and 110" on both sides are lifted to be located in the center, the bent steel plate 116 with a rubber packing 117 attached to the edge and the rubber pad 141 are attached to the exposed reinforcing bar bracket 113. ) Insert into the upper reinforcing bar to form a concave-convex portion, and then mount the cut slabs 110 ', 110 ", so that the edge 103, lower groove 115 is inserted into the convex portion of the bent steel plate 116. To be combined with bolts and nuts (BN), install reinforcing bars 125 and install non-shrink mortar 118 at the bending part, and concrete bracket 104 for pouring rust-preventing shotcrete and exposed reinforcing bar bracket 113 4 methods of mounting to be configured concurrently, By placing several circular concavo-convex 131 on the pressure jaw 101 facing from the central side of the wind slab 110, the male and female are coupled to each other so as not to be displaced from each other, and the binding hole 107 installed at the bottom ) The installation of the binding reinforcing bar 108 inside is a facility for stabilizing the wind speed slab 110 in preparation for seismic waves, and the hook installed with the reinforcing bar in the wind speed slab 110 in the wind guide slab 110 between long legs ( 109) and a wire 112 made of a pc twisted wire and a turnbuckle or cable on the latch 111 installed in the tunnel lining 100 to provide a preparation for the deflection and fall of the wind slab 110, When the cut-off slabs 110', 110" are arranged at a certain angle, the pull-out reinforcing bar 119 is disposed at the edge of the cut-off slabs 110', 110". (105) to set up to function; In installing the cavity 102 in the wind slab 110, the membrane structure 120 is composed of a short side, these joints are wrapped with a cut short side exterior 121, tied with a band, sprinkled with water, and covered with a vinyl 122. After pouring and curing, the air is removed from the membrane structure 120 to recover both the membrane structure 120 and the cut short side exterior 121, so that the cavity 102 can be created, or the long side exterior 133 And the facility using the lubricant 134, In the cross-flow ventilation method that requires a bulkhead 150 facility, a relatively light material is placed between the pressure jaw 101 part protruding from the top of the tunnel wind slab 110 and the crown part and the facility is installed so that it can be fixed, A segmented wind speed slab capable of rapid installation in a tunnel, characterized in that a fireproof material 123 is applied to the lower surface of the installed wind guide slab 110 to protect the structure of the wind guide slab 110 due to a fire in the tunnel 80. structure
机译:本发明设置有风引导板150,导风板150在隧道90中穿过弹簧线91的上侧,以在隧道结构内部供应和排出空气,并且当施加横流法时,风引导板110)安装舱口150,垂直地分隔隧道衬里100的冠部和向上表面侧的压力钳口101和压力钳口101,或者在半交叉流式的情况下,没有舱壁150的隧道在安装内部通风的任何一个设施的隧道风平板200时,突出到隧道衬里100的内部的支架110,并且风平板110分为从支架向上倾斜的两个部分,压力钳口101倾斜,这是突起,形成在中心侧,并且在风引导板110的边缘103侧在横向上形成了多个空腔102,放置在隧道衬里100支架1中04分别从切片板110'和110“的边缘突出。作为拉出的加强杆119的止动件105与隧道衬里100紧密接触,并且压力钳口101是中心侧的突起,在切口板110之间形成相互对接双方'和110英寸。和风平板110,当安装风车板110时,放置隧道坑外部的一侧和另一侧的几组切割板110',110“,并放置在隧道坑外部的另一侧在帽子形状的第一个转向架200'上。把它放在隧道衬里100上,并移动设置在主梁201上的控制液压千斤顶209的行程,使得它可以在提升状态下通过支架104,以及几组风板110),以确保结束103侧同时安装在隧道衬里100的支架104上,如果第一转向架200'横向梁203的上端处的液压千斤顶202的行程逐渐降低,则单件式板坯(110',110“)两侧的压力钳口101彼此自动接触,使得由于其自身重量引起的压缩力101在沿着斜坡的两侧引入板110',110”中帽子。方法和此处,在首先降低设置在第一转向架200'的主束上的控制液压千斤顶209的行程之后,第一转向架200'完全与风平板110分离,然后第一转向架200'是上端。由于链块206设置在2上,使隧道衬里100降低到支架104面上,以形成第一进入转向架200',越过另一个进入的另一个转向架200',以及在隧道外面的风道和移动板坯110到生产现场和院子里;作为另一种方法,第二转向架200“降低设置在主梁201之间的行程,使得横梁203是水平的,然后选择安装在横梁203的任一侧的C形钢207。进入后其他横梁203并进入安装在另一个横梁203上的C梁207,在任一侧上的横梁203形成,以形成不摇动的结构,隧道80,凹坑外风板110制造部位和两个安装方法使其可以移动到院子里;当在安装暴露的加强杆支架113的状态下安装风平板110时,升降和降低了第一转向架中的任何一个的控制液压千斤顶209控制200',并控制第二个转向架200“。 3安装的安装方法,其配置在上述上述露出的加强杆支架113的支架加强杆124,括号104是安装风平板110的障碍物的支架104与现有的形状分开并由一个组成暴露的加强杆支架113,其是隧道衬里110中的水平和倾斜孔11​​4.在嵌入和固定的螺纹型小钢管135的状态下,并且安装和绑定支架加强杆124时,安装和绑定在第二个转向架200“上,侧面切片板(110',110”)露出的加强杆支架113的支架加强杆124穿过安装在103)侧的线路端口132,弯曲钢板116利用附接到边缘的橡胶填料117施加到暴露的加强杆支架113上。在将橡胶垫141放置在插入上部加强杆中以形成不均匀部分的状态之后,切割板安装110'和110“,但边缘103下槽115是弯曲钢板116铁,以配合进入(凸)部分,与螺栓和螺母(Bn)组合,安装加强杆125,并将不可收缩的砂浆118安装到弯曲部分;隧道衬里100上的软支架104间歇地安装,不连续安装 形成一定长度,并且间歇支架104安装有如上所述的暴露的加强杆支架113。暴露的加强杆支架113的支架加强杆124通过安装在沿其两侧的边缘103侧的线路端口132通过,其中两侧的切割板110'和110“被提升为位于中心,弯曲钢板116具有附接到边缘的橡胶填料117和橡胶垫141附接到暴露的加强杆支架113.)插入到上部加强杆中以形成凹凸部分,和然后安装剪切板110',110“,使得边缘103,下槽115插入弯曲钢板116的凸起部分中。与螺栓和螺母(BN)组合,安装加强杆125并安装在弯曲部分的非收缩砂浆118,以及用于浇注防锈的喷射射流和暴露的加强杆支架1134的混凝土支架104通过将多个圆形凸面凸形凸缘131放置在面向上的压力下钳口101上来构造以构成的安装方法M风平板110的中心侧,凸形和母侧彼此连接,以便不彼此移位,并且安装在底部的粘合孔107)内部的装订加强杆108的安装是a用于稳定风速板110以制备地震波的设施,以及在长腿(109)之间的风速板110中的风速板110中的加强杆安装的钩子在长腿(109)和由PC扭曲的线上制成的线112中并且在隧道衬里100中安装在闩锁111上的螺丝扣或电缆,以为风平板110的偏转和落后提供准备,当切断板110',110“以一定角度布置时,拉动-OUT加强杆119设置在截止板110',110“的边缘处。 (105)设置功能;在将腔102安装在风平板110中时,膜结构120由短侧组成,这些接头用切割的短边外部121包裹,与带有带的条带捆扎,用水洒,用乙烯基覆盖。浇注并固化后,从膜结构120移除空气以恢复膜结构120和切割短边外部121,使得可以产生腔102或使用润滑剂的长边外部133和设施。如图134所示,在需要舱壁150设施的横流通风方法中,将相对较轻的材料从隧道风平板110的顶部突出的压力钳口101部分之间放置在突出的压力钳口101部分之间,并且安装了该设施可以固定,一种能够在隧道中快速安装的分段风速板,其特征在于,防火材料123施加到安装的风引导板110的下表面以保护W的结构由于隧道80中的火焰导致板坯110.结构

著录项

  • 公开/公告号KR102321338B1

    专利类型

  • 公开/公告日2021-11-02

    原文格式PDF

  • 申请/专利权人 정인혁;

    申请/专利号KR20180171734

  • 发明设计人 정인혁;정동면;

    申请日2018-12-28

  • 分类号E21F1/04;E21D11/08;E21D11/40;E21F7;

  • 国家 KR

  • 入库时间 2022-08-24 22:26:59

相似文献

  • 专利
  • 外文文献
  • 中文文献
获取专利

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号