首页> 外国专利> Driving and casting procedure for bulbous foot piles - uses concrete rammer inside pile tube with projection above tube being equal to volume of concrete cast

Driving and casting procedure for bulbous foot piles - uses concrete rammer inside pile tube with projection above tube being equal to volume of concrete cast

机译:球根脚桩的驱动和浇筑程序-在桩管内部使用混凝土夯锤,管上方的投影等于混凝土浇筑的体积

摘要

The tube is driven into the foundation bearing ground to the required depth and sufficient concrete is poured into the tube to make a bulbous foot. An internal rammer is then inserted to rest on the concrete, its projection above the tube being equal to the volume of concrete cast. The tube is then partially withdrawn so that top of rammer and punch coincide. Both rammer and tube are now driven down forcing the concrete to take its bulbous form, the rammer and tube are then withdrawn simultaneously, reinforcement is inserted and the remainder of the pile is cast.
机译:将管子打入地基至所需的深度,然后将足够的混凝土倒入管子中以制成球状脚。然后插入一个内部夯锤,使其靠在混凝土上,其在管上方的投影等于混凝土的体积。然后将管子部分抽出,使夯锤和冲头顶部重合。现在将夯锤和管子向下压,迫使混凝土呈球状形式,然后同时撤回夯锤和管子,插入钢筋,其余部分进行浇铸。

著录项

  • 公开/公告号FR2471451B3

    专利类型

  • 公开/公告日1982-09-03

    原文格式PDF

  • 申请/专利权人 HOCHTIEF AG HELFMANN;

    申请/专利号FR19800025760

  • 发明设计人

    申请日1980-12-04

  • 分类号E02D5/44;E02D7/02;E02D7/08;

  • 国家 FR

  • 入库时间 2022-08-22 12:30:08