首页> 外国专利> OPERATION CONTROL METHOD FOR GAS PIPELINE BOOSTING FACILITY

OPERATION CONTROL METHOD FOR GAS PIPELINE BOOSTING FACILITY

机译:天然气管道提升设施的运行控制方法

摘要

PROBLEM TO BE SOLVED: To prevent surge prevention control from being hindered by calculating a recycling start time, a necessary compressor speed and a recycling flowrate, using a flowrate change signal at a gas pipeline demand end, and then operating and controlling a boosting facility on the basis of the calculated values. ;SOLUTION: When a control device receives a gas flowrate change signal from a gas demand end, a recycle start time computation process 101 calculates a time t1 required for a compressor station to become capable of coping with a flowrate change. Furthermore, a compressor speed computation process 102 calculates a compressor speed N1 after the reduction of a gas flowrate and a compressor speed computation process 103 after the lapse of the time t1 finds a compressor speed N2 attainable with a compressor over a time from the beginning of speed reduction to the lapse of the time t1. Then, the larger value of N1 and N2 is selected for use as a set value N for a compressor control device and, then, a difference between a flowrate at an operation point corresponding to N and a flowrate after the reduction is used as a recycling flowrate Q1.;COPYRIGHT: (C)1997,JPO
机译:解决的问题:为防止喘振预防控制受到阻碍,可通过计算再循环开始时间,必要的压缩机速度和再循环流量,使用天然气管道需求端的流量变化信号,然后在运行和控制增压装置上进行操作。计算值的基础。 ;解决方案:当控制设备从燃气需求端接收到燃气流量变化信号时,循环开始时间计算过程101计算压缩机站能够应对流量变化所需的时间t1。此外,压缩机速度计算处理102在减少气体流量之后计算压缩机速度N1,并且在时间t1过去之后从开始算起的时间内找到压缩机可达到的压缩机速度N2之后,计算压缩机速度N2。速度降低到时间t1的经过。然后,选择N1和N2中较大的值作为压缩机控制装置的设定值N,然后,将与N相对应的工作点处的流量与减小后的流量之间的差用作再循环。流量Q1 .;版权所有:(C)1997,日本特许厅

著录项

相似文献

  • 专利
  • 外文文献
  • 中文文献
获取专利

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号