PROBLEM TO BE SOLVED: To provide an underground cavity constructing method, capable of ensuring safe and low-cost construction in a soft ground by making working pits around an underground cavity before drilled and constructed to reinforce the ground, and provide the underground cavity. ;SOLUTION: In a construction method, a plurality of working pits are basically constructed outside a cavity-planed ground with a safe and reliable shield machine and a reinforcing soil zone is formed through the working pits along the vicinity of a cavity to drill a predetermined cavity by using a low-cost mountain tunnel technique. The working pits on reinforcement-necessary sides are refilled if required, the working pits are only refilled for reinforcement without forming the reinforcing soil zone or the working pits are utilized as drain pits 18 if the underground cavity should be reinforced with bolts suspended from the working pits or the underground cavity 15 should be constructed in an aquifer. The working pits are connected to the underground cavity after work is completed to construct the integrated underground cavity to be served as effective pits for ventilation 16, evacuation 17 or others.;COPYRIGHT: (C)1999,JPO
机译:要解决的问题:提供一种地下洞室建造方法,该方法能够通过在钻孔和建造以加固地面并提供地下洞室之前在地下洞室周围制造工作坑来确保在软土地基中安全且低成本的施工。 ;解决方案:在一种施工方法中,基本上是使用安全可靠的屏蔽机在空腔平面内建造多个工作坑,并沿着这些工作坑在空腔附近形成加固土层,以钻出预定的通过使用低成本的山地隧道技术获得空腔。如果需要,可对需要加固的侧面上的工作坑进行重新填充,仅在不形成加固土层的情况下才对工作坑进行填充,以进行加固,或者如果地下空腔应使用从工作中悬挂的螺栓进行加固,则将工作坑用作排水坑18坑或地下空腔15应在含水层中建造。工作完成后,将工作坑连接到地下空腔,以构造集成的地下空腔,以用作通风16,疏散17或其他的有效坑。版权所有:(C)1999,JPO

著录项

相似文献

  • 专利
  • 外文文献
  • 中文文献
获取专利

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号