Method for throwing roadway comprises casting roadway in formwork and progressively displacing it forwards by pulling longitudinal cables until supported by bridge support legs and piles
Method for throwing roadway comprises casting roadway in formwork and progressively displacing it forwards by pulling longitudinal cables until supported by bridge support legs and piles
展开▼
机译:投掷巷道的方法包括将巷道浇筑在模板中,并通过拉动纵向缆索直到由桥梁支脚和桩支撑而逐渐向前移动
展开▼
页面导航
摘要
著录项
相似文献
摘要
The method comprises the construction on site of the roadway (15) by casting in formwork made from a metal frame (10) abutted against the bridge rear support leg (4). A low friction coating (11) is screwed on the frame. The roadway is progressively displaced forwards until it is supported on the piles and the bridge support legs. The forwards displacement is made by sliding inside the formwork playing the role of a guide runner by pulling on longitudinal cables by means of actuators (16). An Independent claim is included for equipment for implementing the method.