首页> 外国专利> METHOD FOR SHORTENING THE CONSTRUCTION PERIOD OF AN RC TYPICAL FLOOR THROUGH COLUMN PRECEDING CONSTRUCTION WHICH ENABLES THE CONCURRENT CONSTRUCTION OF THE RC COLUMN OF A CURRENT FLOOR AND THE RC INTERLAYER STRUCTURE OF THE LOWER FLOOR

METHOD FOR SHORTENING THE CONSTRUCTION PERIOD OF AN RC TYPICAL FLOOR THROUGH COLUMN PRECEDING CONSTRUCTION WHICH ENABLES THE CONCURRENT CONSTRUCTION OF THE RC COLUMN OF A CURRENT FLOOR AND THE RC INTERLAYER STRUCTURE OF THE LOWER FLOOR

机译:缩短RC典型地板贯穿柱的施工周期的方法,可同时进行当前地板的RC柱的构造和下层的RC层状结构

摘要

PURPOSE: A method for shortening the construction period of an RC typical floor through the preceding construction of columns is provided to shorten a construction period for the framework of an RC typical floor by enabling the construction of an RC column according to a construction plan regardless of the concrete being poured into an RC interlayer structure.;CONSTITUTION: A method for shortening the construction period of an RC typical floor through the preceding construction of columns comprises the following steps: constructing RC columns while embedding a dowel bar or a re-bar coupler into joints between the RC interlayer structures and the RC columns; integrating the RC columns with the RC interlayer structures and mounting a horizontal re-bar on the dowel bar or the re-bar coupler while proceeding the previous step; and repeating the above steps.;COPYRIGHT KIPO 2013;[Reference numerals] (A1) Construction supply (A,B Zone); (A2,B2) Division; (A3,B3) Re-bar (ton); (A4,B4) Frame (m^2); (A5,B5) Concrete (m^2); (A6,B6) Slab; (A7,B7) Beam; (A8,B8) Total; (B1) Construction supply (C Zone); (B9) (%) supply compared to A, B zones; (C1) First day; (C2,D2,F2) Beam, a slab, and a frame are installed; (D1) Second day; (D3,E2,F3) Arrangement of bar of a lower beam/PT steel wire installation/arrangement of bar of an upper beam/M&E; (E1) Fourth day; (E3,F4) Arrangement of bar of a lower slab/PT steel wire installation/arrangement of bar of an upper slab/M&E; (E4) Inspecting and depositing Con'C; (F1) Third day
机译:目的:提供一种通过在先柱的构造来缩短RC典型地板的建造周期的方法,以通过使RC柱能够根据施工计划进行建造而缩短RC典型地板的框架的建造周期,而与建造计划无关。组成:一种通过前面的柱子施工来缩短RC典型地板施工周期的方法,包括以下步骤:在埋入销钉或钢筋连接器的同时构造RC柱子进入钢筋混凝土夹层结构和钢筋混凝土柱之间的连接处;将RC柱与RC夹层结构集成在一起,并在继续上一步的同时将水平钢筋安装在销钉或钢筋连接器上; COPYRIGHT KIPO 2013; [参考数字](A1)建筑供应(A,B区);并重复上述步骤。 (A2,B2)部门; (A3,B3)钢筋(吨); (A4,B4)帧(m ^ 2); (A5,B5)混凝土(m ^ 2); (A6,B6)平板; (A7,B7)光束; (A8,B8)总计; (B1)建筑物资(C区); (B9)与A,B区相比的供应量(%); (C1)第一天; (C2,D2,F2)安装了梁,平板和框架。 (D1)第二天; (D3,E2,F3)下梁/ PT钢丝的布置/上梁/ M&E的布置; (E1)第四天; (E3,F4)下板/ PT钢丝的布置/上板/ M&E的布置; (E4)检查并存放Con'C; (F1)第三天

著录项

相似文献

  • 专利
  • 外文文献
  • 中文文献
获取专利

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号