FIELD: mining.;SUBSTANCE: method involves construction of annular transport ramps of opposite direction with single-lane traffic of dump trucks docking in turning platforms, reloading points, construction of open pit sides with triple projections at an inclination angle of 60÷75°, which are separated with safety berms of required width, formation in some part of the open pit field of one of ore bodies of transport ramp (TR) with width providing for two-lane traffic of dump trucks and adjacent to turning platforms, production of ore for both ore bodies by means of a drill-and-fire method so that pillars are left in the open pit sides; delivery of ore to a factory; stripping - to external dumps, construction of underground mine workings and a water drain system; the modification stage involves reconstruction of the eastern side of the open pit (VRT) with partial processing of its pillars and transshipment of dead rocks into an internal dump, change of some part of single-lane transport ramp along the eastern side for a steeply inclined one, transportation of ore from lower horizons of the open pit with articulated dump trucks (ADT) to the transhipment area, transhipment into large dump trucks for delivery to the factory, and creation of a rock cushion at the open pit bottom. Besides, first, from the lower turning platform in the worked-out area of the western side of the open pit (ZRT) there dumped is the main ramp, thus providing transport communication throughout the depth of the open pit; at the open pit side reconstruction stage, a two-lane ramp is in-series formed with projections with a vertical slope and berms of minimum width and rebuilt into a ramp with an increased inclination in opposite direction; a new dump ramp is formed from the turning platform in the south-western part of the open pit; water drainage is relocated to an inter-pipe zone; TR of opposite direction with single-lane traffic along the western side is put out; TR with an increased slope is constructed from the upper turning platform in the north-western part of the open pit; ZRT pillars are mined out; the new dump ramp is enlarged, and loading and transportation of some part of ore is performed from it at mining-out of ZRT pillars by equipment with remote control (RC) to a transhipment point; another part of the ore is transported to VRT bottom, thus creating an ore cushion, and after ZRT pillars are additionally mined out to technologically practical depth, VRT pillars are broken out onto the ore cushion, thus putting out the transport ramp.;EFFECT: improving efficiency and completeness of development of a mineral deposit by an open-pit mining method.;9 cl, 4 dwg
机译:领域:采矿;方法:该方法涉及构造具有相反方向的环形运输坡道,其中自卸车的单车道停靠在转弯平台,重新装载点,具有60÷75°倾斜角的三重投影的露天坑侧面的构造,用所需宽度的安全护栏隔开,在露天矿场的某矿体的某些露天矿场中形成一定宽度的宽度,以提供自卸车的两车道运输,并邻近转弯平台,生产通过钻孔和发射方法对两个矿体进行矿石处理,以使柱子留在露天矿井侧;将矿石运送到工厂;剥离-外部堆放场,地下矿井的建设和排水系统;改造阶段包括对露天矿(VRT)的东侧进行重建,对其支柱进行部分处理,并将死石转运到内部垃圾场,沿东侧改变单车道运输坡道的某些部分,以使其陡峭倾斜一是用铰接式自卸车(ADT)将矿石从露天矿的较低层运输到转运区,再转运到大型的自卸车以运往工厂,并在露天矿的底部形成一块岩石垫层。此外,首先,从露天矿(ZRT)西侧作业区的下部转向平台上倾倒的是主坡道,从而在整个露天矿深度提供运输联系。在露天矿井侧重建阶段,两车道坡道串联形成,这些坡道具有垂直倾斜的凸起和最小宽度的护堤,然后重建为坡度沿相反方向增加的坡道。在露天矿西南部的转弯平台上形成一个新的卸料坡道。排水装置被移至管间区域;沿西侧单车道反方向TR从露天矿西北部的上部转向平台建造斜率增大的TR; ZRT支柱被挖出;扩建新的卸料坡道,并通过带有遥控装置(RC)的设备在ZRT立柱开采时从矿石中进行部分矿石的装载和运输;另一部分矿石被运送到VRT底部,从而形成一个矿石垫层,在ZRT支柱被另外开采到技术上可行的深度之后,VRT支柱被打碎到矿石垫层上,从而推出了运输坡道。通过露天开采方法提高矿藏开发的效率和完整性。; 9 cl,4 dwg

著录项

相似文献

  • 专利
  • 外文文献
  • 中文文献
获取专利

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号