Method of selecting position for offshore substation in the wind power plant and method of designing for power grid design in the wind power plant

机译:风力发电场海上变电站的选位方法及风力发电场的电网设计设计方法

摘要

The present invention relates to a method to select position of a marine substation in a marine wind power generation plant and a method to design a power grid of the marine wind power generation plant. The present invention includes: a step of receiving at least one datum to design a power grid of a marine wind power generation plant producing power from a marine wind power turbine; a step of grouping a plurality of wind power turbines in the marine wind power generation plant; a step of generating at least one initial power grid structure, including internal and external power grids, in accordance with mutual combination orders of the grouped wind power turbines; a step of calculating costs for the internal power grid in accordance with the generated initial power grid structure; a step of selecting a position of a marine substation in the initial power grid structure, corresponding to a minimum cost of the calculated costs for the internal power grid, as a final position of the marine substation; a step of processing the datum for the designing of the power grid of the marine wind power generation plant to generate the datum in a chromosome format; a step of calculating costs for the whole power grid in regard to the generated chromosome; a step of regenerating a chromosome in accordance with the costs for the whole power grid; a step of confirming whether cables in the whole power grid intersect with each other or not; and a step of selecting and designing a structure for the whole power grid, corresponding to a minimum cost of the costs for the whole power grid.
机译:选择海上风力发电站中的海上变电站的位置的方法技术领域本发明涉及一种选择海上风力发电站中的海上变电站的位置的方法以及一种设计该海上风力发电站的电网的方法。本发明包括:接收至少一个数据以设计从海上风力涡轮机发电的海上风力发电厂的电网的步骤;将船用风力发电厂中的多个风力涡轮机分组的步骤;根据分组的风力涡轮机的相互组合顺序,产生至少一个包括内部和外部电网的初始电网结构的步骤;根据生成的初始电网结构计算内部电网成本的步骤;选择海上变电站在初始电网结构中的位置的步骤,其对应于内部电网的计算成本的最小成本,作为海上变电站的最终位置;处理数据以设计海洋风力发电厂的电网以产生染色体格式的数据的步骤;计算与产生的染色体有关的整个电网成本的步骤;根据整个电网的成本再生染色体的步骤;确认整个电网中的电缆是否相交的步骤;选择和设计整个电网的结构的步骤,对应于整个电网成本中的最小成本。

著录项

相似文献

  • 专利
  • 外文文献
  • 中文文献
获取专利

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号