Rutherford-Williamson-Davidson Power Supply Improvement Project: Environmental Impact Statement Scoping Document

机译:Rutherford-Williamson-Davidson电源改进项目:环境影响声明范围文件

获取原文

摘要

The Tennessee Valley Authority (TVA) is proposing to construct, operate and maintain a new or expanded 500-kV substation and associated transmission line upgrades in Middle Tennessee. The substation would be located in Rutherford, Williamson, or Davidson County. Other project components would be located in these counties and in other counties in Middle Tennessee. Following the requirements of the National Environmental Policy Act (NEPA), TVA is preparing an Environmental Impact Statement (EIS) that will evaluate the potential environmental impacts of the construction, operation, and maintenance of the proposed transmission facilities. NEPA regulations require an early and open process for deciding what should be discussed in an EIS the scope of the document. The scoping process involves requesting and using comments from the public and interested agencies to help identify the issues and alternatives that should be addressed in the EIS. This document summarizes the input that TVA has received during the scoping process and defines the scope of the EIS. In addition to agency and public input, the EIS will also address specific requirements associated with a number of other federal laws, such as the Clean Water Act, the Endangered Species Act, and the National Historic Preservation Act.

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号