IN 1998-99, AngloGold Ashanti had planned a pit extension programme at its Navachab gold mine in Namibia that would support production until 2013. At that time, the plant treatment capacity was 170 t/h with an ore throughput of 1.4 Mt/y averaging 1.55 g/t gold. The low price of gold at the time persuaded the company not to proceed. But after a feasibility study, Navachab approved the Western Pushback, which made up half of the original expansion project. This extension of the main pit from 2000 to 2001 extended the life of the mine (LOM) from 2003 to 2005. In 2002-3, another feasibility project was launched to mine the Eastern Pushback. Through reduced costs and a strong gold price, this project was approved and it increased the LOM to 2013.
机译:1998-99年,AngloGold Ashanti计划在其纳米比亚的Navachab金矿进行扩坑计划,该计划将支持直到2013年的生产。当时,该厂的处理能力为170吨/小时,平均矿石产量为1.4吨/年。 1.55克/吨金。当时的黄金价格低廉,使该公司无法继续经营。但经过可行性研究后,Navachab批准了Western Pushback,该项目占原始扩建项目的一半。主矿坑从2000年扩展到2001年,矿山(LOM)的寿命从2003年扩展到2005年。在2002-3年,启动了另一个可行性项目,以开采东部后推。通过降低成本和坚挺的黄金价格,该项目获得批准,并将LOM延长至2013年。

著录项

  • 来源
    《Mining Magazine》 |2007年第3期|共1页
  • 作者

  • 作者单位
  • 收录信息
  • 原文格式 PDF
  • 正文语种 eng
  • 中图分类 矿山开采;
  • 关键词

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号