Titan Resources Ltd will soon rejoin the nickel producer ranks with production from its Armstrong mine due in October. Underground development is due to Start in March next year with first development ore scheduled for May and the move to full scale stope production in August. Ore from the open pit will be mined in six months to produce 2,250 tonnes of contained nickel and will be developed to 100m depth. The decline will Start from the lower half of the pit. The total mineable resource will be 465,000 tonnes at 2.12 percent nickel for just under 10,000t of contained nickel. "It is our intention to use loan facilities to fund the development and keep a substantial amount of our