Ukraine’s Dneprovsky (Dzerzhinsky) Metallurgical Plant plans to commence the first stage of reconstruction at mill 350 in mid-August. According to preliminary data, the unit will be offline from August till December. The stage will involve installation of longs facilities, which will be capable of producing some 670,000 tpy of 8-40 mm rebar, 25-100 mm equal angle and channel No.6.5-10. Besides, re-heating furnace, power substation and associated equipment may be set up.