SHOUGANG JINGTANG COMPLETES 5,500 CU M BF CONSTRUCTION

机译:SHO u gang J ing tang completes 5,500 C um bf construction

获取原文
获取原文并翻译 | 示例
           

摘要

Chinese Hebei-based steelmaker Shougang Jingtang United Iron & Steel (Shougang Jingtang) com- pleted construction of it’s 5,500 cu m blast furnace with commissioning scheduled for late March. Original deadline for this project was February, but completion was slightly delayed, the company’s official said on March 8. The designed capacity of the unit is 4.39 million t of pig iron per year. The BF was built under the capacity replacement programme. However, no facilities were shut down at Shougang Group. Eight smaller blast furnaces at seven other steel companies were announced to be eliminated in order to comply with government requirements (the new to eliminated capacity ratio of 1:1.25). Shougang Jingtang project also includes installation of two converters with a total capacity of 4 million tpy.
机译:中国河北钢铁制造商首钢景塘联合钢铁(首钢京塘)拟合建设的5,500 CU M高炉,预定于3月底预定调试。 该项目的原始截止日期是2月,但完成3月8日表示,完成略有延误,该单位的设计能力为每年439万吨猪铁。 BF是在容量替代计划下构建的。 然而,首钢集团没有关闭任何设施。 八家其他钢铁公司的八家较小的高炉均宣布被淘汰,以遵守政府要求(以1:1.25的淘汰)。 首钢景塘项目还包括安装两个转换器,总容量为400万吨。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号