首页> 外文期刊>Water >HDD (TRENCHLESS) CASE STUDY: STP PROJECT OF SHANXI YAOGUANG COAL POWER COMPANY, PINGYAO COUNTY, SHANXI PROVINCE, CHINA
【24h】

HDD (TRENCHLESS) CASE STUDY: STP PROJECT OF SHANXI YAOGUANG COAL POWER COMPANY, PINGYAO COUNTY, SHANXI PROVINCE, CHINA

机译:HDD(无创)案例研究:山西省平遥县山西耀光煤电公司STP项目

获取原文
获取原文并翻译 | 示例
           

摘要

In 2013, Saint-Gobain PAM China provided materials for a pipeline for the sewage treatment plant (STP) project of the Shanxi Yaoguang Coal Power Company. The pipeline was built to transport the water after wastewater treatment from the STP to the power plant for industrial use. The geographical environment of this project was complex: 1. The level drop between the STP and the power plant was around 200m; and 2. The location of the project had a varied topography. This meant the operation pressure of the pipeline was high. Saint-Gobain PAM China provided pipe and anchored gasket for the project. As Pingyao County is a tourist city, excavation was not allowed in certain areas, so Saint-Gobain PAM China decided to apply trenchless technology to three sections of the total pipeline.
机译:2013年,圣戈班PAM中国为山西耀光煤电公司的污水处理厂(STP)项目的管道提供了材料。修建该管道的目的是将污水处理后的水从STP输送到工业用发电厂。该项目的地理环境复杂:1. STP和电厂之间的水位下降约200m; 2.项目所在地具有不同的地形。这意味着管道的操作压力很高。圣戈班PAM中国为该项目提供了管道和锚固垫片。由于平遥县是一个旅游城市,因此不允许在某些地区进行挖掘,因此圣戈班PAM China决定将非开挖技术应用于总管道的三个部分。

著录项

  • 来源
    《Water》 |2015年第1期|41-41|共1页
  • 作者

  • 作者单位
  • 收录信息
  • 原文格式 PDF
  • 正文语种 eng
  • 中图分类
  • 关键词

相似文献

  • 外文文献
  • 中文文献
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号