COMPUTERISED INFORMATION SYSTEMS: COMPARISON OF RELATIVE IMPACTS ON PLANNED PROJECT DURATION WITHIN A MULTI-PROJECT ENVIRONMENT

机译:计算机信息系统:在多项目环境中对计划项目工期的相对影响的比较

获取原文
获取原文并翻译 | 示例
           

摘要

As more organisations acquire project management computerised information systems (CIS) to ensure the efficient scheduling of projects, there is increasing interest in the extent to which various CIS contribute to a reduction in planned project duration. However, there seems to be no empirical research that suggests that CIS have a positive impact on planned duration or how relative impacts could vary when different CIS are implemented. This paper reports on experimental research that evaluates and draws comparisons between the relative impacts of three CIS on planned project delivery within a specific, real, multi-project environment, and investigates the reasons for such variations. [PUBLICATION ABSTRACT]
机译:随着越来越多的组织使用项目管理计算机信息系统(CIS)来确保项目的有效调度,人们越来越关注各种CIS对减少计划项目工期的贡献。但是,似乎没有经验研究表明CIS对计划的持续时间有积极的影响,或者当实施不同的CIS时相对影响如何变化。本文对实验研究进行了报告,该实验评估了三个CIS在特定,真实,多项目环境中对计划项目交付的相对影响,并进行了比较,并调查了造成这种变化的原因。 [出版物摘要]

著录项

  • 来源
    《South African Journal of Industrial Engineering》 |2008年第1期|p.89-102|共14页
  • 作者

    S Govender H Steyn;

  • 作者单位

    S. Govender1 and H. Steyn22Department of Engineering and Technology ManagementUniversity of Pretoria, South Africaherman.steyn@up.ac.za1 The author was enrolled for the MPM programme at the Department of Engineering and Technology Management, University of Pretoria;

  • 收录信息
  • 原文格式 PDF
  • 正文语种 eng
  • 中图分类
  • 关键词

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号