...
首页> 外文期刊>Shore and beach >Turning a tragedy into large-scale barrier island restoration in Louisiana: A three-project case study
【24h】

Turning a tragedy into large-scale barrier island restoration in Louisiana: A three-project case study

机译:将悲剧转变为路易斯安那州的大规模障碍岛恢复:三个项目的案例研究

获取原文
获取原文并翻译 | 示例
           

摘要

Louisiana has successfully utilized the proceeds from the fines imposed for the Deepwater Horizon incident to significantly jump start barrier island restoration as identified in the Coastal Protection and Restoration Authority (CPRA) of Louisiana Coastal Master Plan (CPRA 2017). The Riverine Sand Mining/ Scofield Island Restoration (BA-40) project was the first to be implemented through a commitment of remaining funds in the initial emergency protective berms' construction budget formulated into the Berms to Barrier Islands plan. The berm/ restoration conversion at Scofield Island was the first to utilize this funding mechanism. The Caminada Headland Beach and Dune Restoration-Increment II (BA-143) project was funded through the National Fish and Wildlife (NFWF) Gulf Environmental Benefit Fund and capitalized on a prior project constructed to the west completing the beach and dune restoration of the entire headland. Lastly, the Caillou Lake Headlands Restoration (TE-100) project was funded through the Natural Resource Damage Assessment (NRDA). The TE-100 project restored the entire degraded beach and dune system backed by a created marsh habitat to complement a prior restoration effort. Scofield Island is located west of the active Mississippi River bird's foot delta in Plaquemines Parish, Louisiana. A primary objective of this project was the excavation and delivery of Mississippi riverine sand for beach and dune restoration; a first in our nation's history. Multiple design and construction challenges arose requiring the CPRA, consulting team, and construction contractor to adapt. Construction of the beach and dune component of this project required approximately 22 miles (mi) of pipeline and four booster pumps along a sediment pipeline corridor that crossed two hurricane protection levees, went underneath two highways and a navigation channel, traversed the Empire Waterway, crossed Pelican Island, entered the Gulf of Mexico, and extended to Scofield Island. The restoration footprint length was approximately 2.4 mi, total volume placed was approximately 3.5 million cubic yards (MCY), and the benefit equaled 510 restored acres (CEC 2014). The pipeline corridor has subsequently been utilized for two other restoration projects, Shell Island East Berm Barrier Island Restoration (BA-110) and Shell Island West NRDA Restoration (BA-111). As a first in Louisiana's restoration history, the Caminada Headland Beach and Dune Restoration-Increments I and II (BA-45 and BA-143) utilized sand dredged from Ship Shoal, an Outer Continental Shelf (OCS) sand resource located approximately 26-38 mi from the restoration areas. The 13.3 mi long headland was restored with approximately 3.7 MCY for BA-45 and 5.5 MCY for BA-143 from the borrow area (CEC 2015 and CEC 2017). A combination of cutterhead dredge/scow barges and hopper dredges were used to construct the project. A key goal of this project was restoring and protecting the fragile ecosystem which provides critical habitat for nesting shorebirds. The headland is of critical importance in serving as a defense of our national energy infrastructure. The western portion of the headland directly protects Port Fourchon, one of the nation's most important energy ports. Caillou Lake Headlands (TE-100), known locally as Whiskey Island, is centrally located in the Isle Dernieres chain and it is a remnant of the single, larger Isle Dernieres (Last Island), which was segmented into multiple smaller islands by a major hurricane in 1856. The project included restoring the beach and dune along approximately 4.5 mi while simultaneously creating a marsh platform along approximately 5,500 feet (ft) utilizing 10.4 MCY of sand from the borrow area (CEC 2018). The borrow area lies within Ship Shoal OCS Lease Block 88 located over 10 mi along the conveyance corridor offshore of Whiskey Island. This project represents the largest barrier island restoration project to date in terms of volume per linear foot of shoreline with an average density of over 441 cubic yards per linear foot (CEC 2018).
机译:路易斯安那州已成功利用对深水地平线事件所处罚款的收益,大大提高了路易斯安那州沿海总体规划(CPRA 2017)海岸保护和修复局(CPRA)所确定的屏障岛的恢复。 Riverine砂矿开采/ Scofield岛修复(BA-40)项目是第一个实施的项目,其承诺是将剩余资金用于最初的紧急保护性护堤的建设预算,该预算已编入Berms to Barrier Islands计划。斯科菲尔德岛的护岸/修复转换是第一个利用这种筹资机制的项目。 Caminada Headland海滩和Dune Restoration-Increment II(BA-143)项目由国家鱼类和野生动物(NFWF)海湾环境效益基金资助,并利用先前在西部建造的项目完成了整个海滩和沙丘的恢复工作岬角。最后,Caillou湖岬角恢复(TE-100)项目由自然资源损害评估(NRDA)资助。 TE-100项目修复了整个退化的海滩和沙丘系统,并建立了沼泽栖息地,以补充先前的修复工作。斯科菲尔德岛位于活跃的密西西比河鸟足三角洲以西,位于路易斯安那州的普拉克明斯教区。该项目的主要目的是密西西比河河沙的开挖和输送,以修复海滩和沙丘。我们国家历史上的第一个。出现了多个设计和施工挑战,需要CPRA,咨询团队和施工承包商进行调整。该项目的海滩和沙丘组成部分的建设需要一条约22英里(mi)的管道和沿着一条沉积物管道走廊的四台增压泵,该走廊穿过两个飓风保护堤,穿过两条高速公路和一条航道,穿过帝国水道,穿过鹈鹕岛,进入墨西哥湾,并延伸到斯科菲尔德岛。恢复的足迹长度约为2.4英里,放置的总体积约为350万立方码(MCY),收益相当于510恢复英亩(CEC 2014)。管道走廊随后被用于另外两个修复项目:壳牌岛东Berm屏障岛修复(BA-110)和壳牌岛西NRDA修复(BA-111)。作为路易斯安那州恢复历史上的第一场,卡米纳达岬角海滩和沙丘恢复增量I和II(BA-45和BA-143)利用从浅滩(大约26-38处的外大陆架(OCS)沙子资源)挖出的沙子。 mi来自修复区。从取土区恢复了13.3英里长的岬角,BA-45约3.7 MCY,BA-143约5.5 MCY(CEC 2015和CEC 2017)。结合使用刀头挖泥船/疏bar船和漏斗挖泥船来构建该项目。该项目的主要目标是恢复和保护脆弱的生态系统,该生态系统为筑巢水鸟提供了重要的栖息地。岬角对于捍卫我们的国家能源基础设施至关重要。岬角的西部直接保护着福尔洪港,该国最重要的能源港口之一。 Caillou Lake Headlands(TE-100),在当地被称为威士忌岛,位于Isle Dernieres链的中心,是单个较大的Isle Dernieres(前岛)的残余,该岛被一个大岛分割为多个小岛1856年的飓风。该项目包括恢复约4.5英里的海滩和沙丘,同时利用借入区域的10.4 MCY沙子在约5500英尺(英尺)的地方创建沼泽平台(CEC 2018)。借用区域位于Whiskey Island离岸运输走廊沿10英里处的Ship Shoal OCS租赁区块88内。该项目是迄今为止最大的屏障岛恢复项目,按海岸线每线性英尺的体积计,平均密度为每线性英尺441立方码以上(CEC 2018)。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号