Despite near-biblical amounts of rain that fell on the Valley of the Sun during February, work continues on the $57.6-million Valley Metro Rail Maintenance of Equipment (MOE) facility, the largest single construction contract for the regional light rail system. The heavy rainfall forced a two-week construction delay throughout much of the facility. According to resident engineer Willie Chiang, the heavy rains have forced construction crews to dry the soil. "There is still too much water in the ground," Chiang said. "Tilling the fill dirt can allow the dirt to dry." Valley Metro Rail spokeswoman Daina Mann said the delay shouldn't cause concern.
机译:尽管二月份的太阳谷雨量接近圣经,但仍在继续进行耗资5760万美元的硅谷地铁设备维护(MOE)设施的工作,这是该地区轻轨系统最大的单一建筑合同。大雨迫使整个工厂的大部分地方推迟了两周的施工。据常驻工程师威利·蒋(Willie Chiang)称,大雨迫使施工人员干燥了土壤。蒋介石说:“地下仍然有太多的水。” “耕种填充污垢会使污垢变干。”山谷地铁的女发言人戴安娜·曼(Daina Mann)说,延误不应引起人们的关注。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号