首页> 外文期刊>Naval Research Logistics >Computing Bounds on Project Duration Distributions for Stochastic PERT Networks
【24h】

Computing Bounds on Project Duration Distributions for Stochastic PERT Networks

机译:计算随机PERT网络的项目工期分布范围

获取原文
获取原文并翻译 | 示例
           

摘要

We consider the PERT model with activities whose durations are random variables with known discrete independent distributions. We develop an algorithm to compute lower and upper bounds for the distribution function of the project duration of the stochastic PERT network. The algorithm is based on conditioning on the longest distances to nodes in the network. In addition, We develop an extension of the Kleindorfer's upper bound. We evaluate the method developed in This paper with some numerical examples.
机译:我们考虑活动持续时间是具有已知离散独立分布的随机变量的活动的PERT模型。我们开发了一种算法来计算随机PERT网络项目工期的分布函数的上下限。该算法基于对与网络中节点的最长距离进行调节的条件。此外,我们开发了Kleindorfer上限的扩展。我们通过一些数值示例来评估本文开发的方法。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号