A Scheduling Method for Painting Line under Pull Production

机译:拉动生产中涂装线的调度方法

获取原文
获取原文并翻译 | 示例
           

摘要

This paper concerns with a scheduling method for painting (preceding) line with much longer production lead-time than assembly (subsequent) line. In general, production schedule of the painting line is made independently based on the forecasted job requirement at the assembly line. When the job requirement changes at the assembly line by virtue of the change of customer order, therefore, production balance is destroyed between the both lines. To avoid the tardiness caused by such unbalance, we need to have many inventories for the painting line. Such countermeasure is taken place in many companies actually. Thus, to avoid the tardiness while keeping small inventory, we propose a scheduling method that makes a Pseudo-Pull production possible for the painting line. We have evaluated the proposed method through computer simulations.
机译:本文涉及一种与生产线(后续)相比,生产提前期要长得多的涂漆(前)生产线调度方法。通常,涂装线的生产计划是根据装配线的预测工作需求独立制定的。因此,当工作要求由于客户订单的改变而在装配线上改变时,两条生产线之间的生产平衡就被破坏了。为了避免这种不平衡引起的拖延,我们需要为涂装线准备许多库存。实际上,许多公司都采取了这种对策。因此,为了避免在保持少量库存的情况下出现拖延现象,我们提出了一种调度方法,该方法可以使涂装线进行伪拉式生产。我们已经通过计算机仿真评估了提出的方法。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号