Assessing the Relationship between Constraint Management and Schedule Performance in Chilean and Colombian Construction Projects

机译:评估智利和哥伦比亚建设项目约束管理与日程绩效的关系

获取原文
获取原文并翻译 | 示例
           

摘要

Construction projects are significantly affected by uncertainty and variability. Traditional management uses result-oriented indicators to control project performance, which present limitations to detecting and preventing deviations. The Last Planner System (LPS) proposes an alternative focused on the systematic task of analyzing the intermediate scope, preparing work, and managing short-term plans through commitments. Although the benefits of LPS have been studied, most quantitative research has focused on work accomplishment metrics, such as the percent plan complete (PPC). This research studied the relevance of work preparation and the relationship between constraint management and project performance. The relationships among work preparation, short-term compliance, and project performance were addressed in five equal progress intervals throughout project execution to study the correlations between PPC, percent constraints removed (PCR), and the schedule performance index (SPI) in 69 construction projects. Also, the correlations between 10 LPS metrics and 3 outcome metrics at project completion were addressed. Then the projects were classified according to their schedule accomplishment outcome to assess differences in 11 LPS metrics. Statistically significant correlations were found among constraint management, short-term compliance, and schedule accomplishment; also, statistically significant differences in constraint management indicators between projects with high and low schedule performance were identified.
机译:建设项目受到不确定性和变异性的显着影响。传统管理使用导向结果的指标来控制项目性能,这对检测和防止偏差产生了限制。最后一个策划系统(LPS)提出了一个替代方案,专注于分析中级范围,准备工作和通过承诺管理短期计划的系统任务。虽然已经研究了LPS的好处,但大多数定量研究都集中在工作成就指标上,例如计划百分比(PPC)。该研究研究了工作准备和制约管理与项目绩效之间的关系。工作准备,短期遵守和项目绩效之间的关系在整个项目执行中以五个相等的进展间隔进行了解决,以研究PPC,百分比(PCR)之间的相关性,以及69个建筑项目中的日程绩效指数(SPI) 。此外,解决了项目完成时10 LPS度量和3个结果指标的相关性。然后,项目按计划完成结果进行分类,以评估11 LPS指标的差异。在约束管理,短期合规性和计划成就下发现了统计学上的相关性;此外,确定了具有高和低调度性能的项目之间的统计学意义的差异。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号