Optimizing the Scheduling of Repetitive Construction to Minimize Interruption Cost

机译:优化重复施工进度以最大程度地降低中断成本

获取原文
获取原文并翻译 | 示例
           

摘要

This paper presents the development of a novel optimization model for the scheduling of repetitive construction projects. The model provides original and unique capabilities that enable planners to search for and identify an optimalear optimal schedule that simultaneously minimizes project duration, crew work interruptions, and interruption costs. The model computations are organized in four major modules: (1)an optimization module that searches for and identifies a near optimal schedule that simultaneously minimizes the project duration, work interruptions, and interruption costs; (2)an initial scheduling module that calculates the early start date and work-continuity total float for each activity in all of its repetitive sections; (3)an intermediate scheduling module that generates a set of feasible schedules that simultaneously minimize project duration and work interruptions; and (4)an interruption cost module that calculates total interruption cost for each of the generated schedules. An application example of a repetitive construction project is analyzed to evaluate model performance and demonstrate its capabilities in optimizing the scheduling of repetitive construction projects.
机译:本文介绍了用于重复建设项目进度计划的新型优化模型的开发。该模型提供了独有的独特功能,使计划人员可以搜索和确定最佳/接近最佳时间表,从而同时将项目工期,人员工作中断和中断成本最小化。模型的计算分为四个主要模块:(1)优化模块,用于搜索和识别接近最佳的进度,同时将项目工期,工作中断和中断成本最小化; (2)初始计划模块,计算每个活动在其所有重复部分的提早开始日期和工作连续性总浮动; (3)中间调度模块,该模块生成一组可行的调度,同时最小化项目工期和工作中断; (4)中断成本模块,其为每个所产生的时间表计算总中断成本。分析了重复建设项目的一个应用示例,以评估模型性能并展示其在优化重复建设项目的进度中的能力。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号