Synchronized Optimization of Various Management-Function Schedules in a Multiproject Environment: Case Study of Planning Steel Girder Fabrication Projects in Bridge Construction

机译:多项目环境中各种管理功能进度表的同步优化:以桥梁施工中钢梁制造项目规划为例

获取原文
获取原文并翻译 | 示例
           

摘要

Structural steel prefabrication is a generally accepted practice in the construction industry conducive to better control of project duration and cost, higher productivity and efficiency, and enhanced quality and safety performance. This study initiated with an investigation of the current practice of major structural steel fabricators in Alberta, where skilled trades rather than fully automated equipment remain the critical resources in production planning and scheduling. How to synchronize the schedules of concurrent projects at different levels to optimize the allocation of fabrication resources (particularly skilled laborers) is identified as a matter of pressing concern in the industry. In collaboration with an industry partner in Edmonton, Alberta, Canada, we (1) developed a unified work breakdown structure (WBS) based on project management functions such as bidding, production planning, estimating, and scheduling; (2) synchronized schedules for various management functions by implementing a dual-level multiproject optimization scheduling framework; and (3) developed a multiproject scheduling tool to implement the research in practice. A case study of the fabrication of steel girders for three bridges investigates the benefits of the proposed scheduling approach to the fabrication process, which include improved alignment between shop operation progress, individual project objectives, and overall program goals.
机译:结构钢的预制是建筑业普遍接受的做法,有助于更好地控制项目工期和成本,提高生产率和效率,并提高质量和安全性能。这项研究始于对艾伯塔省主要结构钢制造商的当前实践的调查,在那里,熟练的行业而非全自动设备仍然是生产计划和调度中的关键资源。如何在不同级别同步并发项目的进度表以优化制造资源(特别是熟练工人)的分配已成为业界迫切关注的问题。我们(1)与加拿大艾伯塔省埃德蒙顿市的行业合作伙伴合作,根据项目管理功能(如投标,生产计划,估算和进度安排)开发了统一的工作分解结构(WBS); (2)通过实施双层多项目优化计划框架来同步各种管理功能的计划; (3)开发了一个多项目计划工具以在实践中进行研究。以三座桥梁的钢梁制造为例,研究了拟议的制造工艺调度方法的好处,其中包括改善车间运营进度,单个项目目标和总体计划目标之间的一致性。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号