首页> 外文期刊>International Journal of Project Management >Discrete time-cost-environment trade-off problem for large-scale construction systems with multiple modes under fuzzy uncertainty and its application to Jinping-II Hydroelectric Project
【24h】

Discrete time-cost-environment trade-off problem for large-scale construction systems with multiple modes under fuzzy uncertainty and its application to Jinping-II Hydroelectric Project

机译:模糊不确定性下多种模式的离散时间 - 环境 - 环境 - 施工系统对多种模式及其在金平 - 二水电项目的应用

获取原文
获取原文并翻译 | 示例
           

摘要

This paper presents a discrete time-cost-environment trade-off problem for large-scale construction systems with multiple modes under fuzzy uncertainty. A multi-objective decision making model is established in which the total project duration is regarded as a fuzzy variable. To deal with the uncertainty, the fuzzy numbers in the model are defuzzified by using an expected value operator with an optimistic-pessimistic index. The objective functions are to minimize the total project cost, project duration, crashing cost, and environmental impact. Furthermore, a fuzzy-based adaptive-hybrid genetic algorithm is developed to find feasible solutions. The one-point crossover and repairing strategy for mutations are designed to avoid infeasible solutions. Finally, the Jinping-II Hydroelectric Project is used as a practical example to demonstrate the practicality and efficiency of the model. Results and a sensitivity analysis are presented to highlight the performance of the optimization method, which proves to be very effective and efficient compared to other algorithms.
机译:本文提出了一种离散的时间 - 环境 - 环境 - 在模糊不确定性下具有多种模式的大规模施工系统的离散时间 - 环境折衷问题。建立了一个多目标决策模型,其中将总项目持续时间视为模糊变量。要处理不确定性,模型中的模糊数通过使用具有乐观悲观索引的预期值运算符来排出。客观职能是最大限度地减少项目总成本,项目持续时间,崩溃成本和环境影响。此外,开发了一种基于模糊的自适应 - 混合遗传算法来寻找可行的解决方案。突变的单点交叉和修复策略旨在避免不可行的解决方案。最后,金平-II水电项目被用作展示模型的实用性和效率的实际例子。结果和灵敏度分析突出了突出了优化方法的性能,这证明与其他算法相比非常有效和高效。

著录项

  • 来源
    《International Journal of Project Management》 |2012年第8期|p.950-966|共17页
  • 作者单位

    State Key Laboratory of Hydraulics and Mountain River Engineering Sichuan University Chengdu 610064 P. R. China Uncertainty Decision-Making Laboratory Sichuan University Chengdu 610064 P. R. China;

    Uncertainty Decision-Making Laboratory Sichuan University Chengdu 610064 P. R. China Chongqing Technique and Business University Chongqing 470004 P. R. China;

    Uncertainty Decision-Making Laboratory Sichuan University Chengdu 610064 P. R. China;

    Ertan Hydropower Development Company Ltd. Chengdu 610051 P. R. China;

    Ertan Hydropower Development Company Ltd. Chengdu 610051 P. R. China;

  • 收录信息 美国《工程索引》(EI);
  • 原文格式 PDF
  • 正文语种 eng
  • 中图分类
  • 关键词

    time-cost-environment; trade-off; construction project; fuzzy; genetic algorithm;

    机译:时间成本环境;权衡;建筑项目;模糊;遗传算法;