Impact of the '5.12' Wenchuan earthquake on Zipingpu concrete face rock-fill dam and its analysis

机译:汶川“ 5.12”地震对紫坪铺混凝土面板堆石坝的影响及分析

获取原文
获取原文并翻译 | 示例
           

摘要

The '5.12' Wenchuan Earthquake hit Zipingpu concrete rock-fill dam hard and rendered a maximum permanent settlement of 100 cm and a horizontal displacement of 60 cm to the dam. Such a large permanent deformation due to earthquake has brought about a large area of separation between the concrete face and the cushion layer plane, resulting in an obvious dislocation of the construction joints of the concrete face above the reservoir water level and a crashed damage of the vertical joints of the concrete face. The damage mechanism has been analysed according to the field investigation. Proposals are also put forward for the future analytical computation of the earthquake impact on the concrete face rock-fill dam, anti-seism design and the principle of rehabilitation of the Zipingpu concrete rock-fill dam after the quake as well.
机译:“ 5.12”汶川地震严重打击了紫坪铺混凝土堆石坝,最大永久沉降为100厘米,坝体水平位移为60厘米。地震造成的如此大的永久变形在混凝土面和垫层平面之间造成了大面积的分离,导致在水库水位以上的混凝土面的施工缝明显错位,并破坏了水库。混凝土面的垂直接缝。根据现场调查分析了其破坏机理。提出了地震对混凝土面板堆石坝地震影响的分析计算,抗震设计以及紫坪铺混凝土堆石坝震后恢复原则的建议。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号