A 1430 MVA synchronous generator from a canceled nuclear power plant has been installed and commissioned at Los Alamos National Laboratory to provide pulsed power and energy for large physics experiments. The authors describe special studies, tests, and design modifications to enable a high-power, steady-state machine to operate as a pulsed, variable-speed generator. The generator rotor and stator core cooling have been changed from hydrogen to air to facilitate the operation. An all-solid-state drive system accelerates the generator rotor from standstill to the maximum operating speed of 2800 rpm and from 1260 rpm to 1800 rpm between load pulses. The excitation system has been modified to provide both the motor and generator mode of operation. The generator is mounted on a spring foundation to minimize the transmission of shaft vibrations into the subsoil. The springs also dampen shocks stemming from the pulsed loads.
机译:洛斯阿拉莫斯国家实验室已安装并调试了一家已取消核电站的1430 MVA同步发电机,并已投入运行,以为大型物理实验提供脉冲功率和能量。作者介绍了特殊的研究,测试和设计修改,以使高功率稳态机器可以用作脉冲变速发电机。发电机转子和定子铁芯的冷却已从氢气改为空气,以方便操作。全固态驱动系统将发电机转子从静止加速到最大运行速度2800 rpm,并在负载脉冲之间从1260 rpm加速到1800 rpm。励磁系统已经过修改,可以同时提供电动机和发电机的运行模式。发电机安装在弹簧基础上,以最大程度地减少轴振动传递到地下土壤中的情况。弹簧还可以减轻脉冲负载产生的冲击。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号