Cable yarding continues to be an efficient and effective harvesting system for the extraction of timber on steep terrain. Modern European silvicultural strategies result in smaller harvest areas, lower extraction volumes and a shift from clear-cut to thinning operations or single tree extraction. Yarder installation time has, especially as a proportion to the extraction time, increased significantly, resulting in higher extraction costs. This study recorded the set-up and take-down time of 79 cable yarder installations. Another 76 installation times were taken from previously published time studies, for a total sample size of 155. The factorial study design differentiated uphill-or downhill yarding, yarder size and whether or not it was the first installation at a landing, or subsequent parallel installation from the same landing area. The covariates recorded were corridor length, terrain slope, number and height of intermediate supports, and number of forest workers. Both a set-up and take-down time models were developed. This will help estimate future cable installation time requirements, and more importantly, provide improved cost estimates for the new silvicultural treatments.
机译:电缆造架继续成为陡峭地形上木材提取的高效有效的收获系统。现代欧洲造林策略导致较小的收获区,降低提取体积和从清除稀释操作或单树提取的偏移。仪式安装时间尤其具有与提取时间的比例,显着增加,导致提取成本更高。本研究记录了79个电缆架式安装的设置和取下时间。另外76次安装时间从前发表的时间研究采取,总样本大小为155.阶乘研究设计差异化了上坡或下坡码,围栏尺寸,以及它是否是着陆时的第一个安装,或者是随后的并行安装。来自同一个着陆区。记录的协变量是走廊长度,地形坡度,中级支持的数量和高度,以及森林工人数量。开发了建立和消耗时间模型。这将有助于估计未来的电缆安装时间要求,更重要的是,为新的造林处理提供改进的成本估算。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号