Time overrun is a major issue in construction projects. Its causes vary, depending upon the nature and size of the project. Developing countries are more susceptible to this problem due to limited resources and lack of managerial skills. This paper focuses on the identification and classification of time overrun factors in public sector projects in Pakistan. Data was collected by the use of a questionnaire given to different professionals in the construction field. Average index (AI) was used to determine each factor’s relative importance. Results indicate that financial difficulties faced by constructor, inadequate planning and scheduling, financial difficulties faced by client, delays in payment by the client, delays in decision making by the client, design mistakes, frequent design changes, material shortage, incompetent sub-constructor assigned by the constructor, poor site management and supervision and inadequate constructor’s experience are the most significant factors of time overrun in public sector construction projects in Pakistan. This study aims to be useful in addressing the issue of time overrun in the construction industry.
机译:时间超支是建筑项目中的主要问题。其原因因项目的性质和大小而异。由于资源有限和缺乏管理技能,发展中国家更容易受到这个问题的影响。本文着重于对巴基斯坦公共部门项目中的时间超支因素进行识别和分类。通过使用问卷向建筑领域的不同专业人士收集数据。平均指数(AI)用于确定每个因素的相对重要性。结果表明,施工人员面临的财务困难,计划和进度安排不充分,客户面临的财务困难,客户付款延误,客户决策延迟,设计错误,频繁的设计变更,材料短缺,不合格的子施工方对于建设者而言,不良的现场管理和监督以及建设者的经验不足是巴基斯坦公共部门建设项目中时间超支的最重要因素。这项研究旨在解决建筑行业的时间超支问题。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号