Construction Technique of Long-Span Shallow-Buried Tunnel Considering the Optimal Sequence of Pilot-Tunnel Excavation

机译:考虑引水隧洞开挖最佳顺序的大跨浅埋隧道施工技术

获取原文
           

摘要

Construction technique considering the optimal sequence of pilot-tunnel excavation was investigated in order to ensure the safety of construction process of long-span shallow-buried tunnel. Firstly, optimal comparisons of the effect of different sequence of pilot-tunnel excavation on the ground settlement were implemented by the numerical analysis. Secondly, an optimal construction method was determined and applied to the construction of a practical tunnel. Some key issues and procedure of the selected construction method were described in detail. Finally, the numerical modeling and calculation of the tunnel construction process were conducted, and the effectiveness of these simulations was demonstrated by using the measured data of the practical tunnel.
机译:为了确保大跨度浅埋隧道施工过程的安全性,研究了考虑引爆隧洞最佳开挖顺序的施工技术。首先,通过数值分析,实现了先导隧道不同开挖顺序对地面沉降影响的最佳比较。其次,确定了最佳施工方法,并将其应用于实用隧道的施工。详细介绍了所选施工方法的一些关键问题和步骤。最后,对隧道施工过程进行了数值建模和计算,并通过实际隧道实测数据验证了模拟的有效性。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号