Delay Causes and Emerging Digital Tools: A Novel Model of Delay Analysis, Including Integrated Project Delivery and PMBOK

机译:延迟原因和新兴的数字工具:一种新型的延迟分析模型,包括集成的项目交付和PMBOK

获取原文
           

摘要

Delay is one of the main challenges of construction projects, and there is still much to overcome in order to reach near zero delay in all construction projects. This project aims to conduct a systematic critical review including a bibliography analysis on delay literature in construction. The main questions consider what has been learnt from a decade investigating delay causes and effects in the construction literature and what factors have been missed in the literature. This paper also presents a new and challenging question regarding how digital tools and associated technologies may prevent any delay in construction projects, which can change the research direction from delay investigations to identifying prevention factors. The paper identifies the delay dataset, including 493 papers investigating delay in construction, and establishes a specific dataset of papers focusing on delay effects and causes (DEC), including 94 selected papers covering different factors examined in over 29 countries such as Iran, India, Turkey, Bangladesh, Saudi Arabia, the United Arab Emirates (UAE), Cambodia, Oman, Malaysia, Taiwan, China, Vietnam, the US, the UK, and Egypt. In addition, the paper identifies 30 critical factors with the frequency of occurrences over three times in the DEC dataset and computes their medians of ranking. This paper also discusses digital tools and methods that can be used for delay analysis and preventions, including MS Project, Oracle Primavera P6, and Open Plan by Deltek. The paper discusses the project schedule delay analysis from project management methodology perspectives. It also discusses the current method’s limitations and future directions, which are based on the identification of the deficiency areas. In total, four overlooked factors are identified and suggested, including faulty data analysis, unmatched structure of the research questionnaires with new knowledge and standards [e.g., Project Management Body of Knowledge (PMBOK)], overlooked effects of digital technologies [e.g., Digital twin, Navisworks, Building Information Model (BIM), Geographic Information System (GIS), and Integrated Project Delivery (IPD)], and ignored job-site technologies. In addition, the paper presents the DEC model for future studies, including four main key factors. These factors are resources (e.g., project budgets, labour, material, equipment, and digital tool), project context, stakeholders performance (e.g., owner/client, consultant/designer, contractor, vendor/supplier), and external factors (e.g., ground condition, site location, regulation, natural disaster), which may significantly affect delay prevention and should be concurrently considered in the future delay investigations, since they may be required for designing an effective mitigation strategy when these proof points are identified. This would significantly help to utilise digital systems to prevent time overruns in different construction contexts.
机译:延迟是建设项目的主要挑战之一,要使所有建设项目的延迟都接近于零,还有很多要克服的问题。该项目旨在进行系统的批判性审查,包括对建筑延误文献的书目分析。主要问题考虑了十年来研究建筑文献中的延误因果的经验教训,以及文献中遗漏了哪些因素。本文还提出了一个新的具有挑战性的问题,关于数字工具和相关技术如何防止建设项目出现任何延误,这可能会改变研究方向,从延误调查到识别预防因素。该论文确定了延误数据集,包括493篇调查施工延误的论文,并建立了一个专门针对延误影响和原因(DEC)的论文数据集,包括94篇精选论文,涵盖了在超过29个国家(例如伊朗,印度,土耳其,孟加拉国,沙特阿拉伯,阿拉伯联合酋长国(UAE),柬埔寨,阿曼,马来西亚,台湾,中国,越南,美国,英国和埃及。此外,本文确定了DEC数据集中出现频率超过三倍的30个关键因素,并计算了它们的排名中位数。本文还讨论了可用于延迟分析和预防的数字工具和方法,包括MS Project,Oracle Primavera P6和Deltek的Open Plan。本文从项目管理方法论的角度讨论了项目进度延迟分析。它还讨论了当前方法的局限性和未来方向,这些方向和局限性基于对缺陷区域的识别。总共确定并提出了四个被忽略的因素,包括错误的数据分析,具有新知识和新标准的研究调查表的结构不匹配[例如,项目管理知识体系(PMBOK)],数字技术的被忽略的影响[例如,数字孪生,Navisworks,建筑信息模型(BIM),地理信息系统(GIS)和综合项目交付(IPD)],而忽略了工作现场技术。此外,本文还提出了用于未来研究的DEC模型,其中包括四个主要关键因素。这些因素是资源(例如,项目预算,劳动力,材料,设备和数字工具),项目背景,利益相关者的绩效(例如,所有者/客户,顾问/设计人员,承包商,卖方/供应商)和外部因素(例如,地面状况,工地位置,法规,自然灾害),这可能会严重影响延误预防,因此在以后的延误调查中应同时考虑这些因素,因为在确定这些证据点时,可能需要它们来设计有效的缓解策略。这将大大有助于利用数字系统来防止在不同施工环境下的时间超支。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号