Combining contemporary and traditional project management tools to resolve a project scheduling problem

机译:结合现代和传统项目管理工具来解决项目进度问题

获取原文
获取原文并翻译 | 示例
           

摘要

In this paper we examine a construction project involving the building of large concrete slabs for three buildings in an office park complex. There are finish-to-start (FS) as well as start-to-start (SS) and finish-to-finish (FF) precedence relationships among the project activities. We prepare an initial project schedule using Microsoft Project and manually validate the results using the precedence diagramming method (PDM) procedure. When the client informs us that the schedule must be shortened we find that Microsoft Project does not have the capability for resolving our particular time/cost tradeoff issues. So we revert to the traditional approach for resolving time/cost tradeoffs in projects and develop an original linear programming formulation for the time/cost tradeoff problem when a project is modeled as a precedence diagram. By combining contemporary (Microsoft Project) and traditional (a linear programming time/cost tradeoff model) project management tools we are able to successfully resolve the scheduling issues associated with the slab construction project. Further, we demonstrate the anomalous effects of start-to-start (SS) and finish-to-finish (FF) relationships via our construction project example in which the solution to the time/cost tradeoff problem requires that certain activities be lengthened in order to shorten the project duration.
机译:在本文中,我们检查了一个建筑项目,其中涉及在办公园区内为三栋建筑物建造大型混凝土板。项目活动之间存在从头开始(FS)以及从头开始(SS)和从头到尾(FF)的优先关系。我们使用Microsoft Project准备初始项目进度表,并使用优先级图示方法(PDM)程序手动验证结果。当客户通知我们必须缩短时间表时,我们发现Microsoft Project不具有解决我们特定的时间/成本权衡问题的能力。因此,当项目建模为优先图时,我们将恢复为解决项目中时间/成本权衡的传统方法,并为时间/成本权衡问题开发原始的线性规划公式。通过将现代的(Microsoft Project)和传统的(线性编程时间/成本折衷模型)项目管理工具相结合,我们能够成功解决与平板建筑项目相关的调度问题。此外,通过我们的建筑项目示例,我们演示了开始到开始(SS)和完成到完成(FF)关系的异常影响,其中时间/成本权衡问题的解决方案要求某些活动必须按顺序进行延长缩短项目工期。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号