Managing construction schedule by telepresence: Integration of site video feed with an active nD CAD simulation

机译:通过网真管理施工进度:现场视频源与活动nD CAD仿真的集成

获取原文
获取原文并翻译 | 示例
           

摘要

In recent years, the increased utilization of building information modeling (BIM) has brought attention to the need for BIM-based operation systems that provide a decision-making feature in addition to visual information: This study constructed a project schedule management system that integrates the data points of an nD computer aided design (CAD) object (e.g., schedule and resource information) with a telepresence concept video management operation system. A methodology was developed that allows the user to monitor the current construction status relative to the design and verify the completion of the facility through real-time comparison between the planned process represented by the nD object and the actual image of the construction site sent from an on-site webcam. An active nD CAD system was developed that possesses features such as a comparative simulation between the on-site image and a 4D object to minimize interference between processes and a 5D object that is specialized to the resource mobilization level of the field. A telepresence-based nD CAD system was developed based on this methodology, and the practicality of the system was verified by webcams installed on a bridge construction site. Thus, the project manager is not only able to utilize the nD object for visualization but is also able to use the system as a decision-making system to formulate the most appropriate project schedule by comparing the nD object with the actual on-site image. (C) 2016 Elsevier B.V. All rights reserved.
机译:近年来,对建筑信息模型(BIM)利用率的提高引起了人们对基于BIM的操作系统的需求的关注,该操作系统除了提供视觉信息外还提供决策功能:本研究构建了一个项目进度管理系统,该系统集成了带有网真概念视频管理操作系统的nD计算机辅助设计(CAD)对象的数据点(例如进度表和资源信息)。开发了一种方法,允许用户监视与设计相关的当前施工状态,并通过实时比较由nD对象表示的计划过程与从ND发送的施工现场的实际图像来验证设施的完成情况。现场网络摄像头。开发了一种主动nD CAD系统,该系统具有一些功能,例如在现场图像和4D对象之间进行比较模拟,以最大程度地减少过程与专门针对该领域的资源动员水平的5D对象之间的干扰。基于此方法开发了基于网真的nD CAD系统,并通过安装在桥梁施工现场的网络摄像头验证了该系统的实用性。因此,项目经理不仅可以利用nD对象进行可视化,而且还可以将该系统用作决策系统,通过将nD对象与实际现场图像进行比较来制定最合适的项目进度表。 (C)2016 Elsevier B.V.保留所有权利。

著录项

  • 来源
    《Automation in construction》 |2016年第8期|32-43|共12页
  • 作者单位

    Gyeongsang Natl Univ, Engn Res Inst, Dept Civil Engn, Jinju 660701, South Korea;

    Gyeongsang Natl Univ, Dept Civil Engn, Jinju 660701, South Korea;

    Korea Inst Construct Technol, ICT Convergence & Integrat Res Div, Goyang Si 411712, Gyeonggi Do, South Korea;

    Seoul Natl Univ Sci & Technol, Dept Civil Engn, 232 Gongneung Ro, Seoul 139743, South Korea;

  • 收录信息
  • 原文格式 PDF
  • 正文语种 eng
  • 中图分类
  • 关键词

    Telepresence; nD CAD; Webcam; BIM; Decision making;

    机译:远程呈现;nD CAD;网络摄像头;BIM;决策制定;