Cost-based scheduling method using object-oriented approach

机译:面向对象的基于成本的调度方法

获取原文
获取原文并翻译 | 示例
           

摘要

Cost and schedule performances share common variables for effective project control. However, the real-world implementations of breakdown structures for cost and schedule are at different levels of detail, which makes the integration of cost and schedule information quite complex. Given the pressing need for an effective yet relatively easy-to-compile approach, this research proposes an innovative scheduling approach that enables contractors to develop a schedule based on the pay items in the contract during the tendering and construction phase. By using Microsoft Visual C#, a system with the proposed approach is implemented and, thus, pay items and schedule information are automatically integrated. A case study is investigated to demonstrate the merits of this system. The research shows a true synchronization between the cost and schedule functions and provides useful insights into future project planning and scheduling in construction projects. (C) 2016 Elsevier B.V. All rights reserved.
机译:成本和进度绩效共享有效的项目控制的共同变量。但是,成本和进度明细结构的实际实现在不同的详细程度上,这使得成本和进度明细信息的集成非常复杂。鉴于迫切需要一种有效但相对易于编译的方法,这项研究提出了一种创新的进度计划方法,使承包商能够在招标和施工阶段根据合同中的付款项目制定进度表。通过使用Microsoft Visual C#,可以实现具有所提出方法的系统,从而自动集成了付款项目和时间表信息。案例研究表明了该系统的优点。该研究显示了成本和进度功能之间的真正同步,并为建设项目中的未来项目计划和进度安排提供了有用的见解。 (C)2016 Elsevier B.V.保留所有权利。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号