Extra High Voltage (EHV) transmission corridor siting studies are complex and costly procedures, which are often prolonged by technical, public, institutional, and state regulatory factors. The primary goal of this research is to contribute to a more predictable and expedient siting study. The following objectives are accomplished: (1) Exploration and description of technical and methodological aspects of siting in terms of the general approach to the siting study, impact assessment techniques, data collection and mapping considerations. (2) Exploration and description of the following public and institutional considerations in the siting study: public participation, active opposition, media coverage, attitudes of affected agencies, and communication among involved organizations. Determination of the effects of these considerations on the siting process. (3) Review and evaluation of the state siting regulations in terms of: clarity of requirements, technical siting requirements, coordination of actions in the study, coordination with other relevant regulations, and public and agency participation in the study. Identification of the effects of the state regulations on the siting study process. (4) Development of guidelines for improved EHV transmission corridor siting studies.;The principal methodology of the research is the single case study of Wyoming-Cloverdale 765 kV siting project, which represents a model of a contemporary, interstate, EHV siting study. The results of the case study are complemented by the review of state siting regulations and the literature.;The major outcome of the research are the guidelines for improved corridor siting studies. The guidelines are developed for corridor siting study consultants, electric utility companies, and state regulatory commissions.;Findings of the research indicate that technical, public, institutional, and state regulatory factors interactively affect the process of the corridor siting study. Furthermore, the siting study has dominant political overtones, and as such cannot be treated as a merely technical project. Public opposition to new EHV transmission lines can significantly increase the effects of technical, public, institutional, and regulatory deficiencies, reducing the probability of line approval.;The testing of the guidelines in siting study practice, and a multiple case study research dealing with the same considerations and their interactions, are suggested for future research.
机译:特高压(EHV)输电走廊选址研究是复杂且昂贵的程序,通常会因技术,公共,机构和州监管因素而延长。这项研究的主要目的是为更可预测和更方便的选址研究做出贡献。实现以下目标:(1)从选址研究的一般方法,影响评估技术,数据收集和制图考虑方面探讨和描述选址的技术和方法论方面。 (2)在选址研究中探索和描述以下公共和机构注意事项:公众参与,积极反对,媒体报道,受影响机构的态度以及相关组织之间的沟通。确定这些考虑因素对选址过程的影响。 (3)从以下方面审查和评估州选址法规:要求的明确性,技术选址要求,研究活动的协调,与其他相关法规的协调以及公众和机构参与研究的协调。确定国家法规对选址研究过程的影响。 (4)制定改进超高压输电走廊选址研究的指南。该研究的主要方法是怀俄明-克罗弗代尔765 kV选址项目的单例研究,它代表了当代跨州超高压选址研究的模型。案例研究的结果得到了州选址法规和文献的补充。;研究的主要成果是改进走廊选址研究的指南。该指南是为走廊选址研究顾问,电力公司和州监管委员会制定的;研究结果表明,技术,公共,机构和州的监管因素相互作用地影响走廊选址研究的过程。此外,选址研究具有主要的政治色彩,因此不能仅视为技术项目。公众反对新的超高压输电线路会大大增加技术,公共,机构和监管缺陷的影响,降低线路批准的可能性。选址研究实践中准则的测试,以及涉及选址研究实践的多案例研究相同的考虑因素及其相互作用,建议用于未来研究。

著录项

  • 作者

    Crnojacki, Zorica.;

  • 作者单位

    Virginia Polytechnic Institute and State University.;

  • 授予单位 Virginia Polytechnic Institute and State University.;
  • 学科 Environmental Sciences.;Urban and Regional Planning.
  • 学位 D.E.D.P.
  • 年度 1994
  • 页码 376 p.
  • 总页数 376
  • 原文格式 PDF
  • 正文语种 eng
  • 中图分类
  • 关键词

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号