Project schedule review: Delay causes and mitigation strategies for hospital renovation projects.

机译:项目进度审查:医院翻新项目的延误原因和缓解策略。

获取原文
获取原文并翻译 | 示例

摘要

Both the current and forecast expansion of capital projects in the healthcare industry in Canada are significant. Delivering projects on time in a health care setting is critical to the ongoing operational aspects of a hospital. This thesis is a comprehensive and objective review of project schedule delays in health care facility renovation projects. The study identifies the list of project schedule delay causal factors, and their corresponding frequency and magnitude for a sample population of a project typical in an acute care facility. Distinct patterns were revealed. Solution strategies to reduce or eliminate the causal factors were also generated. In addition, a review of project schedule overrun was completed. A key result of the study is the identification of the causes of project schedule delays and corresponding strategies to reduce their occurrence.
机译:加拿大医疗行业目前和预期的资本项目扩展都意义重大。在医疗机构中按时交付项目对于医院的日常运营至关重要。本文是对医疗设施改造项目中项目进度延误的全面客观审查。该研究确定了项目进度延误因果的列表,以及它们在急救设施中典型项目样本人群的相应频率和大小。揭示了不同的模式。还产生了减少或消除因果因素的解决方案策略。此外,已完成对项目进度超支的审查。该研究的关键结果是确定项目进度延误的原因以及减少此类情况发生的相应策略。

著录项

  • 作者

    Pankiw, Apollinaria.;

  • 作者单位

    University of Calgary (Canada).;

  • 授予单位 University of Calgary (Canada).;
  • 学科 Engineering Civil.
  • 学位 M.Sc.
  • 年度 2005
  • 页码 265 p.
  • 总页数 265
  • 原文格式 PDF
  • 正文语种 eng
  • 中图分类 建筑科学;
  • 关键词

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号