BIOLOGICAL TREATMENT OF COKE PLANT WASTEWATERS: CONCEPT TO COMPLIANCE IN NINE MONTHS

机译:焦化厂废水的生物处理:九个月的合规性概念

获取原文
获取原文并翻译 | 示例

摘要

The New Boston Coke Corporation entered an agreement with the U.S. EnvironmentalrnProtection Agency on April 1, 1998 to have an operating biological treatment facility forrnthe processing of ammonia stripped coke plant wastewater by December 31, 1998. Tornaccomplish this assignment in the given nine-month schedule, Chester Engineersrnselected a field-erected package treatment unit which would process 120 gpm ofrnwastewater. This unit would operate in extended aeration mode to provide nitrificationrnof the nitrogenous waste load; provisions were also provided for up-front selectorrndenitrification. This fast track installation/construction process required a phasedrnparallel path engineering, procurement, and construction, and a team effort of bothrnengineers and constructors dedicated to delivering the facility on schedule. Thernfacility was designed, installed/constructed and started-up on schedule and within arnlimited budget.
机译:新波士顿可乐公司于1998年4月1日与美国环境保护局签订了一项协议,要拥有一个运行中的生物处理设施,以在1998年12月31日之前处理氨气脱除的焦化厂废水。Torn完成给定的九个月时间表,切斯特工程师选择了一个现场安装的包装处理装置,该装置可以处理120加仑/分钟的废水。该装置将在扩展曝气模式下运行,以提供含氮废物的硝化作用。还提供了预先选择器脱硝的规定。这种快速的安装/建造过程需要分阶段的平行路径工程,采购和建造,并且工程师和建造者需要全力以赴按时交付设施。该设施是按计划并在有限的预算范围内设计,安装/建造和启动的。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号