RUNNING RESULTS OF THE SPL DETOXIFYING PILOT PLANT IN CHALCO

机译:中铝SPL排毒试点厂运行结果

获取原文
获取原文并翻译 | 示例

摘要

A new process to detoxify SPL had been developed in Chalco in December 2003, and the first SPL detoxifying pilot plant of China had been established in Chalco by the end of 2004. During the past five months of 2005, the pilot plant has been put into running. Till the end of May 2005, 104 tons SPL have been detoxified, and 119 tons innoxious solid residue has been received for processing. The average soluble F~- and CN~- in the solid residue are respectively 39.7mg/l and 0.053mg/l, which are lower than China national permitted discharge standard 50.0mg/l and 1.0mg/l, the final product is benign. Now the pilot plant is working well, and experiments on how to make use of the benign SPL solid residue are processing.
机译:中国铝业已于2003年12月开发了一种新的SPL脱毒工艺,并于2004年底在中国铝业建立了中国第一家SPL脱毒中试工厂。在2005年的过去五个月中,该中试工厂已投入运营。运行。到2005年5月底,已对104吨SPL进行了排毒,并接收了119吨无毒固体残渣进行加工。固体残留物中的平均可溶性F〜-和CN〜-分别为39.7mg / l和0.053mg / l,低于中国国家许可的排放标准50.0mg / l和1.0mg / l,最终产品是良性的。现在,中试工厂运转良好,正在进行有关如何利用良性SPL固体残渣的实验。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号