Analysis of Binjin UHVDC restart failure and relevant suggestions on secure and stable operation of power grid

机译:Binjin UHVDC重启失败的分析及关于电网安全稳定运行的相关建议

获取原文

摘要

On July 2nd,2017,Pole I of Binjin UHVDC failed to recover after two restart attempts,which impact both the sending-end and receiving-end system.First of all,the detailed process of restart function is presented and the impacts on frequency and voltage are analyzed.Secondly,the main impacts on both sending-end and receiving-end system are studied by replaying the failed recovery of Binjin UHVDC in the simulation,and the possible risks caused by improper restart strategy,unreasonable power flow arrangement and malfunctions of HVDC control system in the process are analyzed.On this basis,some suggestions are proposed in order to reduce the impact of HVDC restart and ensure security and stability of both sending-end and receiving-end system.
机译:于2017年7月2日,Binjin UHVDC的杆I在两次重启尝试后未能恢复,这会影响发送结束和接收端系统。首先,提出了重启功能的详细过程,并且对频率的影响和影响 分析了电压。第二,通过在模拟中重放Binjin UHVDC的失败恢复来研究对发送端和接收端系统的主要影响,以及由重启策略不合理,不合理的功率流量排列和故障引起的可能风险 HVDC控制系统在此过程中进行了分析。在此基础上,提出了一些建议,以减少HVDC重启的影响,确保发送端和接收端系统的安全性和稳定性。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号