Early warning look ahead metrics: The Percent Milestone Backlog metric

机译:预警前瞻指标:里程碑里程碑积压百分比指标

获取原文

摘要

This paper describes the purpose, development methodology, and utility of the Percent Milestone Backlog metric that was jointly developed by National Aeronautics and Space Administration (NASA) Goddard Space Flight Center (GSFC) and The Aerospace Corporation to monitor the execution performance of GSFC flight projects that are under development. All complex development projects experience delays and corresponding backlogs of their project control milestones during their acquisition lifecycles. As part of a larger set of Early Warning Look Ahead metrics that were developed to monitor GSFC projects' cost and schedule performance, the Percent Milestone Backlog metric is particularly revealing, and has utility as a stand-alone execution performance monitoring tool that measures performance independently of Earned Value Management (EVM), and provides insights of project performance relative to historical successful projects. Monthly milestone backlog data were collected on a large collection of historical NASA flight projects. The backlog data were converted to a percent backlog relative to the planned milestone completion performance, and were then normalized to cover the period of acquisition from Preliminary Design Review (PDR) to Launch Readiness Date (LRD). From this normalized dataset, a “region of normality” was discovered that depicts historical percent milestone backlog versus time. This region describes the maximum and minimum percent backlog observed by the historical projects at any stage of their acquisition lifecycle beginning at PDR. Given this region, the metric then plots the percent backlog performance of a project that is being monitored as a function of time from PDR to the present. Those projects whose percent backlog falls within the “region of normality” as described by the historical projects are considered “healthy,” and behaving normally despite their backlog. On the other hand, those projects whose percent backlog falls outside the “region of normality” are considered to be at risk of a schedule overrun, and worthy of further intervention. Furthermore, the “region of normality” is subdivided into “shades of normality,” providing an indication that a currently “healthy” project may be headed for trouble. The Percent Milestone Backlog metric provides actionable insight (independent of EVM) to GSFC management on the milestone execution performance of GSFC flight project acquisitions. But the method could easily be extended to any kind of commodity that can extract similar performance data. For NASA, this method could be applied to other centers such as Marshall Space Flight Center or Kennedy Space Center. The method could also be applied to other agencies and organizations. GSFC management has found the Percent Milestone Backlog metric to be an important tool in their management oversight toolkit.
机译:本文介绍了由国家航空航天局(NASA)戈达德太空飞行中心(GSFC)和航空航天公司联合开发的,用于监视GSFC飞行项目执行绩效的里程碑里程碑积压百分比指标的目的,开发方法和效用。正在开发中。所有复杂的开发项目在购置生命周期中都会遇到延迟和相应的项目控制里程碑积压。作为用于监视GSFC项目的成本和进度绩效而开发的更大范围的“提前预警”度量标准的一部分,“里程碑里程碑积压”度量标准尤其具有启发性,并且可作为独立的执行绩效监视工具来独立测量绩效挣值管理(EVM),并提供与历史成功项目相关的项目绩效见解。每月里程碑积压数据是从大量历史悠久的NASA飞行项目中收集的。积压数据转换为相对于计划的里程碑完成绩效的积压百分比,然后进行标准化以涵盖从初步设计评审(PDR)到发射准备日期(LRD)的采购周期。从该标准化数据集中,发现了一个“正常区域”,该区域描述了历史积压的里程碑百分比与时间的关系。此区域描述了从PDR开始的历史项目在其收购生命周期的任何阶段所观察到的最大和最小未完成百分比。在给定该区域的情况下,该指标然后绘制从PDR到现在的时间函数,该项目的积压性能百分比正在受监视。那些积压百分比处于历史项目所描述的“正常区域”之内的项目被视为“健康”,尽管积压,它们的行为正常。另一方面,那些积压百分比不在“正常范围”内的项目被认为存在进度超支的风险,值得进一步干预。此外,“正常区域”细分为“正常阴影”,这表明当前“健康”的项目可能会遇到麻烦。里程碑积压百分比指标为GSFC管理人员提供了关于GSFC飞行项目收购的里程碑执行绩效的可操作见解(独立于EVM)。但是该方法可以很容易地扩展到可以提取相似性能数据的任何种类的商品。对于NASA,此方法可以应用于其他中心,例如马歇尔太空飞行中心或肯尼迪航天中心。该方法也可以应用于其他机构和组织。 GSFC管理层发现,“里程碑里程碑积压百分比”指标是其管理监督工具包中的重要工具。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号