首页> 外文会议>International conference on vibration, structural engineering and measurement >Studies on Aseismatic Performance of a Typical Subway Tunnel with Initial Defects Caused by Construction of New Down-Through Tunnels
【24h】

Studies on Aseismatic Performance of a Typical Subway Tunnel with Initial Defects Caused by Construction of New Down-Through Tunnels

机译:典型地铁隧道与初期缺陷造成的初期缺陷的抗震性能研究

获取原文

摘要

For the engineering background of subway tunnel with initial defects caused by the construction of new down-through tunnels, the aseismatic performance of the existed tunnel is studied so as to reveal the mechanism of seismic dynamic response by using finite difference method.Numerical simulation shows that the tunnel is deforming in its entirety since such physical variables as velocity, displacement and stress in its all key weak points have same dynamic tendency under influence of approaching construction of tunnels, and these variables are much larger than those without any influence.After down-through construction, much influences of aseismatic performance are mainly taking place at both the side wall and the upper arch, and the shearing damage are mainly doing in surrounding soil mass.Due to widely shearing damage after down-through construction, it is suggested that grouting reinforcing should be applied so as to make them much stiffness as a whole.
机译:对于地铁隧道的工程背景具有初始缺陷引起的新贯穿隧道,研究了隧道的良期性性能,以揭示使用有限差分方法来揭示地震动态响应的机制。数值模拟显示由于这种物理变量作为速度,在其所有关键弱点的速度,位移和应力的情况下,隧道的整体变形是在接近隧道的施工的影响下具有相同的动态倾向,并且这些变量远大于没有任何影响的变量。在下降 - 通过施工,在侧壁和上拱门都主要发生了很多影响,侧壁和上拱形都是在周围的土壤质量上进行剪切损坏。在施工后造成广泛的剪切损坏,建议灌浆应申请增强,以使它们整体僵硬。

著录项