Analysis of long-span prestressed concrete bridge based on the method of “zero bending moment of dead load”

机译:基于“恒载零弯矩”方法的大跨度预应力混凝土桥梁分析

获取原文

摘要

At present main problems of long-span prestressed concrete girder bridges designed by traditional theory are excessive midspan sag. While the zero bending moment method can effectively reduce the structural deformation, using the prestressed bending moment to balance the moment produced by weight. At the basis of analysis on the traditional design theory and the zero bending moment method, the formula for calculating the effective prestress of each segment was derived according to the principle of “zero bending moment of dead load”. Above two methods were used on the four bridges for comparison analysis, and the results showed that with the zero bending moment method, the stress difference of each section and deflection were smaller, ant that the structure had a strong safety reserve. It verified that the design theory of “zero bending moment of dead load” played a positive role on improving the deflection.
机译:目前,采用传统理论设计的大跨度预应力混凝土梁桥存在的主要问题是中跨垂度过大。虽然零弯矩法可以有效地减少结构变形,但使用预应力弯矩来平衡由重量产生的弯矩。在对传统设计理论和零弯矩法进行分析的基础上,根据“恒载零弯矩”原理,推导了各节段有效预应力的计算公式。在四座桥梁上采用以上两种方法进行对比分析,结果表明,采用零弯矩法时,各断面的应力差和挠度较小,从而保证了结构的安全储备。验证了“静载荷零弯矩”的设计理论对改善挠度起到了积极作用。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号